Loading...
2025/04/25 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet SCR Apr 28th - May 4th Closure Start Description Department Street/Intersection Date IMI 1 Hobson Ln Forreslridge Dr Country Club Rd 05/08/25 07/30/25 Utility work and turn lane construction on Public Works Inspections Gavin Petner Full Closure Hobson 2 Oak St E(109) Austin St at Intersection 05/19/25 07/04/25 ADA/Sidewalk Work at Intersection Streets Roy San Miguel Lane Closure 3 Redstone Rd Hercules Ln Neptune Dr 05/0S/25 06/12/25 Utilities and Pavement replacement Engineering Dante Hale Full Closure 4 Tawakoni or(5908) Amistad Ln at Intersection 05/19/25 06/27/25 ADA Ramp Repair Streets Roy San Miguel Lane Closure 5 Trinity Rd McKinney St Blagg Rd 05/05/25 06/06/25 Utilities and Pavement replacement Engineering Dante Hale Full Closure Exported on April 25,2025 11:43:14 AM CDT 2 Street Closure Report: Current Closures smartsheet Department Department C���� 1 Aileen St Panhandle St Broadway St 09/27/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. Audra Ln Stockton St Mockingbird Ln 07/29/24 05/09/25 Connection new storm drainage Private Development Zabdiel Mota Lane Closure 2 to existing City of Denton drainage. 3 Austin St N(208) Pecan St W @ Intersection 03/31/25 05/09/25 ADA/Sidewalk Repair Streets Roy San Miguel Lane Closure 4 Ave A Collins St Eagle or 10/08/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 5 Ave A Eagle or Highland St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Rolling Closure pavement replacement. 6 Ave B Fannin St Margie St 11/22/24 05/30/25 Pavement replacement Engineering Scott Fettig Full Closure 7 Ave C Eagle or Highland St 08/26/24 04/30/25 Pavement replacement. Engineering Scott Fettig Full Closure 8 Ave G Prairie St Lousie St 03/13/25 05/23/25 Utility installations and Engineering Megan Davidson Full Closure pavement replacement 9 Bernard St Lindsey St Fannin St 08/26/24 05/30/25 Utility installations and Engineering Scott Fettig Rolling Closure pavement replacement. 10 Bonnie Brae St Airport Rd(FM 1515) Walt Parker or(Main Stadium Dr) 01/06/25 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 11 Cactus Cir Yucca or (End of street)Cul de sac 04/28/25 09/02/25 Utilities and Pavement Engineering Dante Hale Full Closure replacement 12 Camelot St Hercules Ln Stuart Rd 04/28/25 07/01/25 Utilities and Pavement Engineering Dante Hale Rolling Closure replacement 13 Clear River Ln Montecito or Sweet Cloud Way 04/07/25 05/23/25 Concrete Panel Repair Streets Roy San Miguel Lane Closure 14 Clover Ln Robinwood Ln Glenwood Ln 11/12/24 05/18/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure 15 Collins St Ave A Bernard St 08/26/24 05/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 16 Congress St Ponder St Carroll Blvd 03/31/25 06/01/25 Utility construction Engineering Megan Davidson Rolling Closure 17 Congress St Ponder Ave Colt St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 18 Crescent St Carroll Blvd Bolivar St 01/24/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. Eagle or Ave C Ave A 03/17/25 05/09/25 Using it or an entrance due to Public Works Inspections Collin Cole Lane Closure 19 elevation changes in the jobsite it is the only way to get into the site Eastpark Blvd Linden or Crescent St 04/28/25 05/26/25 Jobsite needs to be able to Public Works Inspections Collin Cole Full Closure 20 access the buildings with cranes but cant do that from inside jobsite 21 Ector St Emry St University Dr 04/28/25 05/26/25 Sanitary Sewer Being installed Public Works Inspections Collin Cole Lane Closure in the Northbound lane 22 Emery St Alice St Dead End(West of Fulton) 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 23 Fry St Oak St Hickory St 04/28/25 05/16/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure 24 Fulton St Cordell St Emery St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 25 Hickory Creek Rd Riverpass or Country Club Rd(FM 1830) 03/13/23 12/31/25 Bridge Installation Engineering Tracy Beck Full Closure 26 Hillcrest St Panhandle St Crescent St 12/27/23 04/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 27 Huisache St Aspen or Yucca or 04/09/25 08/08/25 Utilities and Pavement Engineering Dante Hale Rolling Closure replacement Jim Christal Masch Branch Rd @ Intersection 03/07/25 05/02/25 Adding 2 Lanes E/W on Jim Public Works Inspections Kirk Winter Lane Closure 28 Christal:Adding a turn Lane on Masch Branch 29 Johnson St Collins St Smith St 04/14/25 05/09/25 Sewer connection Public Works Inspections Stephany Trammell Lane Closure 30 Juno Ln Atlas or Stuart or 04/09/25 08/08/25 Utility installations and Engineering Scott Fettig Rolling Closure pavement replacement. 31 Margie St Ave A Ave B 11/01/24 05/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 32 Morse St Loop 288 Mayhill Rd 12/02/24 06/27/25 Water Line Replacement and Public Works Inspections Kristine Stewart Lane Closure Road Reconstruction Streets Water 33 Mounts Ave Congress St W Haynes St 03/21/25 06/27/25 Utility installations and Engineering Megan Davidson Full Closure pavement replacement Exported on April 25,2025 11:43:33 AM CDT Streett Intersection From To Closure Start Closure End n Department Department Contact Date Date Descriptio Closure Type 34 Mulberry St Elm St Carroll Blvd 03/17/25 05/09/25 Water/Wastewater connections Public Works Inspections Stephany Trammell Full Closure 35 Mulberry St Welch St Bernard St 11/29/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 36 Nautical Ln Hickory Creek Rd Ocean Or 04/28/25 05/30/25 Water and Storm line tie ins Private Development Gavin Petner Lane Closure 37 Northridge St Hinkle or Bolivar St 04/16/25 04/20/26 Utilities and Pavement Engineering Dante Hale Rolling Closure replacement 38 Oak St Carroll Blvd Fry St 04/21/25 05/26/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure 39 Oak St Welch St Ave C 04/28/25 05/30/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure 40 Ocean Dr Atlantic Dr Nautical Ln 04/14/25 05/07/25 Sanitary Sewer install Private Development Gavin Petner Full Closure 41 Panhandle St Ector St Aileen St 09/27/24 05/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 42 Prairie St Welch St Bernard St 03/13/25 05/23/25 Utility installations Engineering Megan Davidson Full Closure 43 Precision or Airport Rd LINT Library Annex 04/01/25 07/31/25 Reconstruction Engineering Other Gio Pineiro Full Closure Riney Rd Bonnie Brae St Hardaway Rd 03/08/25 08/01/25 Contractor to install 12-inch Engineering Jesus Perez Full Closure 44 waterline to provide water to the new DISD elementary school 45 Robinwood Ln Emerson Ln Live Oak St 11/12/24 05/16/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure 46 Robinwood Ln Live Oak Kayewood Dr 01/27/25 06/30/25 Road reconstruction(Milling Engineering Sheldon Gatewood Full Closure and C/G Removal,Stabilization) 47 Saddle Back or Quarter Horse Way Highpoint or 04/28/25 05/23/25 Sidewalk and Panel Repairs Streets Roy San Miguel Lane Closure 48 Scripture St Jagoe St Ponder St 03/04/25 10/17/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 49 Sunset St University Dr W Anna St 01/20/25 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 50 Unicorn Lake Blvd State School Rd Wind River Ln 03/25/25 05/30/25 Water tie ins Private Development Gavin Petner Lane Closure 51 Welch St Oak St Hickory St 04/21/25 05/05/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Full Closure 52 Welch St Eagle Or Highland St 03/13/25 05/30/25 Utility installations and Engineering Megan Davidson Full Closure pavement replacement 53 Welch St Eagle or Hickory St 06/03/24 05/31/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 54 Welch St Chestnut St Mulberry St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 55 Welch St Highland St Hickory St 08/26/24 07/31/25 Utility installations and Engineering Scott Fettig Rolling Closure pavement replacement. 56 Westway St Anna St Bolivar St 01/24/25 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 57 Willowwood St Westwood Or Leslie St 03/10/25 05/07/25 Sanitary sewer,water and Private Development Gavin Petner Lane Closure storm sewer install Exported on April 25,2025 11:43:33 AM CDT 3 Street Closure Report: Completed Closures smartsheet Street/ •-r - - •-• • Description Depaent Department Contact • - •- Audra Ln Stockton St Mockingbird Ln 02/24/25 04/18/25 Paving new addition street lane Private Development Public Zabdiel Mota Lane Closure on Audra Lane and replacing Works Inspections 1 street panel on existing roadway where 8-inch water tap was performed. 2 Bell Ave N(3317) Locust St Holly Creek Rd 03/03/25 04/11/25 Curb Gutter/Sidewalk Repair Streets Roy San Miguel Lane Closure 3 Bonnie Brae St Oak St Hickory St 02/10/25 04/05/25 Concrete poles install on that Public Works Inspections John Cantu Lane Closure corner for DM Bonnie Brae St University Dr(Hwy 380) Elm St N 03/10/25 04/18/25 Contractor will be preparing the Engineering Jesus Perez Rolling Closure 4 right-of-way by cutting down the trees that will be removed to widen Bonnie Brae Bronco Way Chivalry Dr Bonnie Brae St 03/31/25 04/15/25 Contractor will be boring Engineering Jesus Perez Lane Closure 5 underneath the intersection of Bonnie Brae and Bronco Way to install a 12-inch water line 6 Duncan St Smith St Kerley St 02/21/25 04/25/25 Water Utility Line Repairs- Public Works Inspections Kirk Winter Lane Closure Repairing Asphalt 7 Fannin St Ave A Ave B 12/09/24 04/11/25 Storm Drain being installed Public Works Inspections Collin Cole Lane Closure 8 Hialeah Dr(4200) Vineland Ave @ Intersection 04/07/25 04/17/25 Street Panel/ADA/Sidewalk Streets Roy San Miguel Lane Closure Repair 9 Hill St Smith St Mill St 02/21/25 04/25/25 Water Utility tie-in Public Works Inspections Kirk Winter Lane Closure 10 Hollister Ln(1900) Fanitia PI @ Intersection 04/07/25 04/17/25 ADA/Sidewalk Repair Streets Roy San Miguel Lane Closure 11 Houston PI Thomas St Bradley St 09/27/24 04/11/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. Kenwood St Wilderness St Fox Hollow 11/18/24 03/28/25 Reconstruction of the road curb Streets Jesus Rodriguez Full Closure 12 and gutter mill subgrade stabilization 13 Lakeside Ct Lake Country Dr Cul de Sac 03/03/25 04/11/25 Sidewalk Repair Streets Roy San Miguel Lane Closure 14 Marietta St Oak St Scripture St 09/27/24 04/11/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 15 Oak St E(109) Austin St N Locust St N 03/31/25 04/25/25 Sidewalk/Curb Repair Streets Roy San Miguel Lane Closure 16 Pinto Dr(2820) Paint Dr at Intersection 02/24/25 03/28/25 Street Panels and Sidewalk Streets Roy San Miguel Lane Closure Repair 17 Spur Ct Lake Country Dr Cul de Sac 03/03/25 04/11/25 Sidewalk Repair Streets Roy San Miguel Lane Closure 18 Thomas St Panhandle St Emery St 10/11/24 03/31/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. Exported on April 25,2025 11:43:51 AM CDT