2025/05/02 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet SCR May 5th - 11 th Street/Intersection Date re IMI Description Department Department Contact Closure Type 1 Ave D Chestnut St Mulberry St 05/12/25 08/15/25 Utility installations and pavement replacement. Engineering Megan Davidson Full Closure 2 Chestnut St Ave C Ave D 05/12/25 08/15/25 Utility installations and pavement replacement. Engineering Megan Davidson Full Closure 3 Crescent St Aileen St Malone St 05/21/25 07/21/25 Utility installations and pavement replacement. Engineering Megan Davidson Full Closure Hilltop Rd at Country Club Road(FM 1830) 05/12/25 09/30/25 Hilltop Road at Country Club Road will be Other Tracy Beck Full Closure 4 reconstructed(new drainage,road,etc.)and new northbound right turn lane will be added to Country Club Road 5 Oak St E(109) Austin St at Intersection 05/19/25 07/04/25 ADA/Sidewalk Work at Intersection Streets Roy San Miguel Lane Closure 6 Ryan Rd Creekside Dr Granada Td 05/12/25 05/15/25 Sanitary Sewer improvement Public Works Inspections Alexander Cervantes Full Closure Wastewater 7 Tawakoni Dr(5908) Amistad Ln at Intersection 05/19/25 06/27/25 ADA Ramp Repair Streets Roy San Miguel Lane Closure 8 Union Cir(in entirety) Chestnut St Prairie St 05/12/25 10/01/25 Utility installations and pavement replacement. Engineering Megan Davidson Full Closure Exported on May 2,2025 11:57:11 AM CDT 2 Street Closure Report: Current Closures smartsheet . ilimm Description 17Ajleen St Panhandle St Broadway St 09/27/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 2St Panhandle St Crescent St 05/02/25 12/05/25 Utility installations and Engineering Megan Davidson Full Closure pavement replacement. Audra Ln Stockton St Mockingbird Ln 07/29/24 05/09/25 Connection new storm drainage Private Development Zabdiel Mote Lane Closure 3 to existing City of Denton drainage. 4 Austin St N(208) Pecan St W @ Intersection 03/31/25 05/09/25 ADA/Sidewalk Repair Streets Roy San Miguel Lane Closure 5 Ave A Collins St Eagle Dr 10/08/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 6 Ave A Eagle or Highland St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Rolling Closure pavement replacement. 7 Ave B Fannin St Margie St 11/22/24 05/30/25 Pavement replacement Engineering Scott Fettig Full Closure 8 Ave G Prairie St Lousie St 03/13/25 05/23/25 Utility installations and Engineering Megan Davidson Full Closure pavement replacement 9 Bernard St Lindsey St Fannin St 08/26/24 05/30/25 Utility installations and Engineering Scott Fettig Rolling Closure pavement replacement. 10 Bonnie Brae St Airport Rd(FM 1515) Walt Parker or(Main Stadium Dr) 01/06/25 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 11 Cactus Cir Yucca or (End of street)Cul de sac 04/28/25 09/02/25 Utilities and Pavement Engineering Dante Hale Full Closure replacement 12 Camelot St Hercules Ln Stuart Rd 04/28/25 07/01/25 Utilities and Pavement Engineering Dante Hale Rolling Closure replacement 13 Clear River Ln Montecito or Sweet Cloud Way 04/07/25 05/23/25 Concrete Panel Repair Streets Roy San Miguel Lane Closure 14 Clover Ln Robinwood Ln Glenwood Ln 11/12/24 05/18/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure 15 Collins St Ave A Bernard St 08/26/24 05/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 16 Congress St Ponder St Carroll Blvd 03/31/25 06/01/25 Utility construction Engineering Megan Davidson Rolling Closure 17 Congress St Ponder Ave Coit St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 18 Crescent St Carroll Blvd Bolivar St 01/24/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. Eagle or Ave C Ave A 03/17/25 05/09/25 Using it or an entrance due to Public Works Inspections Collin Cole Lane Closure 19 elevation changes in the jobsite it is the only way to get into the site Eastpark Blvd Linden or Crescent St 04/28/25 05/26/25 Jobsite needs to be able to Public Works Inspections Collin Cole Full Closure 20 access the buildings with cranes but cant do that from inside jobsite 21 Ector St Emry St University or 04/28/25 05/26/25 Sanitary Sewer Being installed Public Works Inspections Collin Cole Lane Closure in the Northbound lane 22 Egan St Carroll Blvd Bolivar St 05/07/25 09/10/25 Utility installations and Engineering Megan Davidson Full Closure pavement replacement. 23 Emery St Alice St Dead End(West of Fulton) 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 24 Fry St Oak St Hickory St 04/28/25 05/16/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure 25 Fulton St Cordell St Emery St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 26 Hickory Creek Rd Riverpass or Country Club Rd(FM 1830) 03/13/23 12/31/25 Bridge Installation Engineering Tracy Beck Full Closure 27 Hobson Ln Forrestridge or Country Club Rd 05/08/25 07/30/25 Utility work and turn lane Public Works Inspections Gavin Petner Full Closure construction on Hobson 28 Huisache St Aspen or Yucca or 04/09/25 08/08/25 Utilities and Pavement Engineering Dante Hale Rolling Closure replacement Jim Christal Masch Branch Rd @ Intersection 03/07/25 06/06/25 Adding 2 Lanes E/W on Jim Public Works Inspections Kirk Winter Lane Closure 29 Christal:Adding a turn Lane on Masch Branch 30 Johnson St Collins St Smith St 04/14/25 05/09/25 Sewer connection Public Works Inspections Stephany Trammell Lane Closure 31 Juno Ln Atlas or Stuart or 04/09/25 08/08/25 Utility installations and Engineering Scott Fettig Rolling Closure pavement replacement. 32 Margie St Ave A Ave B 11/01/24 05/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 33 Mistywood Ln Robinwood Glenwood 04/28/25 05/16/25 Voids underground Other Sheldon Gatewood Full Closure Exported on May 2,2025 11:57:27 AM CDT Streett Intersection From To Closure Start Closure End Date Date Description Department Department Contact Closure Type 34 Morse St I Loop 288 Mayhill Rd 12/02/24 06/27/25 Water Line Replacement and Public Works Inspections Kristine Stewart Lane Closure Road Reconstruction Streets Water 35 Mounts Ave Congress St W Haynes St 03/21/25 06/27/25 Utility installations and Engineering Megan Davidson Full Closure pavement replacement 36 Mulberry St Elm St Carroll Blvd 03/17/25 05/09/25 Water/Wastewater connections Public Works Inspections Stephany Trammell Full Closure 37 Mulberry St Welch St Bernard St 11/29/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 38 Nautical Ln Hickory Creek Rd Ocean or 04/28/25 05/30/25 Water and Storm line tie ins Private Development Gavin Petner Lane Closure 39 Normal St Oak St Scripture St 05/08/25 09/05/25 Utility installations and Engineering Megan Davidson pavement replacement. 40 Northridge St Hinkle or Bolivar St 04/16/25 04/20/26 Utilities and Pavement Engineering Dante Hale Rolling Closure replacement 41 Oak St Carroll Blvd Fry St 04/21/25 05/26/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure 42 Oak St Welch St Ave C 04/28/25 05/30/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure 43 Ocean Dr Atlantic Dr Nautical Ln 04/14/25 05/30/25 Sanitary Sewer install Private Development Gavin Petner Full Closure 44 Panhandle St Ector St Aileen St 09/27/24 05/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 45 Pershing or Atlas Dr Stuart Rd 05/08/25 12/15/25 Utilities and Pavement Engineering Dante Hale Full Closure replacement 46 Prairie St Welch St Bernard St 03/13/25 05/23/25 Utility installations Engineering Megan Davidson Full Closure 47 Precision or Airport Rd UNT Library Annex 04/01/25 07/31/25 Reconstruction Engineering Other Gio Pineiro Full Closure 48 Redstone Rd Hercules Ln Neptune or 05/05/25 06/12/25 Utilities and Pavement Engineering Dante Hale Full Closure replacement Riney Rd Bonnie Brae St Hardaway Rd 03/08/25 08/01/25 Contractor to install 12-inch Engineering Jesus Perez Full Closure 49 waterline to provide water to the new DISD elementary school 50 Robinwood Ln Emerson Ln Live Oak St 11/12/24 05/16/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure 51 Robinwood Ln Live Oak Kayewood Dr 01/27/25 06/30/25 Road reconstruction(Milling Engineering Sheldon Gatewood Full Closure and C/G Removal,Stabilization) 52 Saddle Back Dr Quarter Horse Way Highpoint or 04/28/25 05/23/25 Sidewalk and Panel Repairs Streets Roy San Miguel Lane Closure 53 Scripture St Jagoe St Ponder St 03/04/25 10/17/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 54 Sunset St University or W Anna St 01/20/25 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 55 Trinity Rd McKinney St Blagg Rd 05/05/25 06/06/25 Utilities and Pavement Engineering Dante Hale Full Closure replacement 56 Unicorn Lake Blvd State School Rd Wind River Ln 03/25/25 05/30/25 Water tie ins Private Development Gavin Petner Lane Closure 57 Welch St Oak St Hickory St 04/21/25 05/16/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Full Closure 58 Welch St Eagle or Highland St 03/13/25 05/30/25 Utility installations and Engineering Megan Davidson Full Closure pavement replacement 59 Welch St Eagle or Hickory St 06/03/24 05/31/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 60 Welch St Chestnut St Mulberry St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 61 Welch St Highland St Hickory St 08/26/24 07/31/25 Utility installations and Engineering Scott Fettig Rolling Closure pavement replacement. 62 Westway St Anna St Bolivar St 01/24/25 06/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 63 Willowwood St Westwood or Leslie St 03/10/25 05/30/25 Sanitary sewer,water and Private Development Gavin Petner Lane Closure storm sewer install Exported on May 2,2025 11:57:27 AM CDT 3 Street Closure Report: Completed Closures smartsheet 'DescriptionStr -•. - Department •__ •-r - - •-• • • - •- Audra Ln Stockton St Mockingbird Ln 02/24/25 04/18/25 Paving new addition street lane Private Development Public Zabdiel Mota Lane Closure on Audra Lane and replacing Works Inspections 1 street panel on existing roadway where 8-inch water tap was performed. 2 Ave C Eagle Dr Highland St 08/26/24 04/30/25 Pavement replacement. Engineering Scott Fettig Full Closure 3 Bell Ave N(3317) Locust St Holly Creek Rd 03/03/25 04/11/25 Curb Gutter/Sidewalk Repair Streets Roy San Miguel Lane Closure 4 Bonnie Brae St Oak St Hickory St 02/10/25 04/05/25 Concrete poles install on that Public Works Inspections John Cantu Lane Closure corner for DM Bonnie Brae St University Dr(Hwy 380) Elm St N 03/10/25 04/18/25 Contractor will be preparing the Engineering Jesus Perez Rolling Closure 5 right-of-way by cutting down the trees that will be removed to widen Bonnie Brae Bronco Way Chivalry or Bonnie Brae St 03/31/25 04/15/25 Contractor will be boring Engineering Jesus Perez Lane Closure 6 underneath the intersection of Bonnie Brae and Bronco Way to install a 12-inch water line 7 Duncan St Smith St Kerley St 02/21/25 04/25/25 Water Utility Line Repairs- Public Works Inspections Kirk Winter Lane Closure Repairing Asphalt 8 Fannin St Ave A Ave B 12/09/24 04/11/25 Storm Drain being installed Public Works Inspections Collin Cole Lane Closure 9 Hialeah Dr(4200) Vineland Ave @ Intersection 04/07/25 04/17/25 Street Panel/ADA/Sidewalk Streets Roy San Miguel Lane Closure Repair 10 Hill St Smith St Will St 02/21/25 04/25/25 Water Utility tie-in Public Works Inspections Kirk Winter Lane Closure 11 Hillcrest St Panhandle St Crescent St 12/27/23 04/30/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 12 Hollister Ln(1900) Fanitia PI @ Intersection 04/07/25 04/17/25 ADA/Sidewalk Repair Streets Roy San Miguel Lane Closure 13 Houston PI Thomas St Bradley St 09/27/24 04/11/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 14 Lakeside Ct Lake Country or Cul de Sac 03/03/25 04/11/25 Sidewalk Repair Streets Roy San Miguel Lane Closure 15 Marietta St Oak St Scripture St 09/27/24 04/11/25 Utility installations and Engineering Scott Fettig Full Closure pavement replacement. 16 Oak St E(109) Austin St N Locust St N 03/31/25 04/25/25 Sidewalk/Curb Repair Streets Roy San Miguel Lane Closure 17 Spur Ct Lake Country or Cul de Sac 03/03/25 04/11/25 Sidewalk Repair Streets Roy San Miguel Lane Closure Exported on May 2,2025 11:59:23 AM CDT