2025/06/20 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR June 23rd - 29th
Street/Intersection Closure Start Descriptio Department Department Contact Closure Type
Date IMl-
1 Cordell St C0"St Fulton St 06/30/25 09/26/25 Full road reconstruction Engineering Megan Davidson Full Closure
2 Welch St Sycamore St Mulberry St O6/30/25 10/06/25 Full road reconstruction Engineering Megan Davidson Full Closure
3 Yellowstone PI Hercules Ln Juno Ln 06/30/25 09/01/25 utilities and Pavement replacement Engineering Dante Hale Full Closure
Exported on June 20,2025 11:50:16 AM CDT
2 Street Closure Report: Current Closures smartsheet
ti t Description Department
Aileen St Panhandle St Broadway St 09/27/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
Airport Rd(FM 1515) 135 E Frontage Rd Airport/135W Frontage Rd 07/07/25 07/14/25 Construction of the new Engineering Robin Davis Full Closure
2 alignment of Bonnie Brae
connecting to Airport Road/FM
1515
3 Alice St Sunset St University or(US 380) 05/27/25 06/30/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
4 Alice St Panhandle St Crescent St 05/02/25 12/05/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
5 Ave A Collins St Eagle or 10/08/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
6 Ave A Eagle or Highland St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
7 Ave B Fannin St Margie St 11/22/24 06/30/25 Pavement replacement Engineering Scott Fettig Full Closure
8 Ave D Chestnut St Mulberry St 05/12/25 08/15/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
9 Ave G Prairie St Lousie St 03/13/25 06/27/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
10 Bonnie Brae St Airport Rd(FM 1515) Walt Parker or(Main Stadium Dr) 01/06/25 07/14/25 Utility installations and Engineering Robin Davis Full Closure
pavement replacement.
Bonnie Brae St S Willowwood St Parvin St 06/23/25 10/24/25 Installation of drainage Engineering Robin Davis Full Closure
infrastructure,embankment
11 work in advance of street
widening. (Access to Natl
Wholesale&residents only)
12 Cactus Cir Yucca or (End of street)Cul de sac 04/28/25 09/02/25 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
13 Camelot St Hercules Ln Stuart Rd 04/28/25 07/01/25 Utilities and Pavement Engineering Dante Hale Rolling Closure
replacement
14 Chestnut St Ave C Ave D 05/12/25 08/15/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
15 Clover Ln Robinwood Ln Glenwood Ln 11/12/24 07/12/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure
16 Congress St Ponder St Coit St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
17 Congress St Ponder St Carroll Blvd 03/31/25 07/04/25 Utility construction Engineering Megan Davidson Rolling Closure
18 Crescent St Carroll Blvd Bolivar St 01/24/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
19 Crescent St Aileen St Malone St 05/21/25 07/21/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
20 Crescent St Aileen St Malone St 06/16/25 09/05/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
21 Denton St Hickory St Congress St 06/02/25 11/05/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
Eagle or Ave C Ave A 03/17/25 08/29/25 Using it or an entrance due to Public Works Inspections Collin Cole Lane Closure
22 elevation changes in the jobsite
it is the only way to get into the
site
23 Egan St Carroll Blvd Bolivar St 05/07/25 09/10/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
24 Emery St Alice St Dead End(West of Fulton) 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
25 Fry St Oak St Hickory St 04/28/25 06/27/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure
26 Fulton St Cordell St Emery St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
27 Granada Trail Granada Trail Seville Rd 06/16/25 06/27/25 installing sewer pipe Wastewater John,Cantu Lane Closure
28 Hickory Creek Rd Riverpass or Country Club Rd(FM 1830) 03/13/23 12/31/26 Bridge Installation Engineering Tracy Beck Full Closure
Hilltop Rd at Country Club Road(FM 1830) 05/27/25 09/30/25 Hilltop Road at Country Club Engineering Tracy Beck Full Closure
Road will be reconstructed(new
29 drainage,road,etc.)and new
northbound right turn lane will
be added to Country Club Road
30 Hobson Ln Forrestridge or Country Club Rd 05/08/25 07/01/25 Utility work and turn lane Public Works Inspections Gavin Petner Full Closure
construction on Hobson
Exported on June 20,2025 11:50:23 AM CDT
Streett Intersection From To Closure Start Closure End
Date Date Description Department Department Contact Closure Type
31 Huisache St Aspen Dr Yucca Dr 04/09/25 08/08/25 Utilities and Pavement Engineering Dante Hale Rolling Closure
replacement
Jim Christal Rd Masch Branch Rd @ Intersection 03/07/25 07/11/25 Adding 2 Lanes E/W on Jim Public Works Inspections Kirk Winter Lane Closure
32 Christal:Adding a turn Lane on
Masch Branch
33 Juno Ln Atlas Dr Stuart Dr 04/09/25 08/08/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
34 La Mirada(1500) Manten Blvd Zilda Way 06/09/25 07/04/25 Concrete Panel Repair Streets Roy San Miguel Lane Closure
35 Margie St Ave A Ave B 11/01/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
36 Mistywood Ln Robinwood Ln Glenwood Ln 04/28/25 07/12/25 Voids underground Other Sheldon Gatewood Full Closure
37 Mockingbird Ln Mingo Rd University Dr(U.S.380) 06/16/25 07/18/25 Bore work to install new Private Development Zabdiel Mote Lane Closure
sanitary sewer line.
38 Morse St Loop 288 Mayhill Rd 12/02/24 06/27/25 Water Line Replacement and Public Works Inspections Kristine Stewart Lane Closure
Road Reconstruction Streets Water
39 Mounts Ave Congress St W Haynes St 03/21/25 06/27/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
40 Mulberry St Welch St Bernard St 11/29/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
41 Mulberry St Elm St Carroll Blvd 03/17/25 07/11/25 Water/Wastewater connections Public Works Inspections Stephany Trammell Full Closure
42 Normal St Oak St Scripture St 05/08/25 09/05/25 Utility installations and Engineering Megan Davidson
pavement replacement.
43 Northridge St Hinkle Dr Bolivar St 04/16/25 04/20/26 Utilities and Pavement Engineering Dante Hale Rolling Closure
replacement
44 Oak St Carroll Blvd Fry St 04/21/25 07/11/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure
45 Oak St Welch St Ave C 04/28/25 07/11/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure
46 Oak St E(109) Austin St at Intersection 05/19/25 07/04/25 ADA/Sidewalk Work at Streets Roy San Miguel Lane Closure
Intersection
47 Ocean Dr Atlantic Dr Nautical Ln 04/14/25 07/15/25 Sanitary Sewer install Private Development Gavin Petner Full Closure
48 Pershing Dr Atlas Dr Stuart Rd 05/08/25 12/15/25 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
49 Ponder Ave Oak St W Broadway St 06/02/25 12/31/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
50 Ponder St Oak St Panhandle St 06/19/25 04/27/26 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
51 Prairie St Welch St Bernard St 03/13/25 06/27/25 Utility installations Engineering Megan Davidson Full Closure
52 Precision Or Airport Rd LINT Library Annex 04/01/25 07/31/25 Reconstruction Engineering Other Gio Pineiro Full Closure
53 Redstone Rd Hercules Ln Neptune Dr 05/05/25 06/12/26 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
Riney Rd Bonnie Brae St Hardaway Rd 03/08/25 08/11/25 Contractor to install 12-inch Engineering Jesus Perez Full Closure
54 waterline to provide water to the
new DISD elementary school
55 Robinwood Ln Live Oak Kayewood Dr 01/27/25 06/30/25 Road reconstruction(Milling Engineering Sheldon Gatewood Full Closure
and C/G Removal,Stabilization)
56 Robinwood Ln Emerson Ln Live Oak St 11/12/24 07/12/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure
57 Robson Ranch Rd Frontage Rd(SB) Briarwood Rd 06/20/25 06/24/25 Grading of new right turn lanes Private Development Public Gary Hatfield Lane Closure
Works Inspections Other
58 Scripture St Jagoe St Ponder St 03/04/25 10/17/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
59 Selene Dr Neptune Dr Stuart Rd 06/04/25 11/28/25 Engineering Scott Fettig Full Closure
60 Seven Oaks Ln(7912) Clear River Ln @ Intersection 06/23/25 07/18/25 Sidewalk Repair Streets Roy San Miguel Lane Closure
61 Stuart Rd Hercules Ln Kings Row 06/09/25 06/30/25 Offsite utility work for Landmark Public Works Inspections Alexander Cervantes Lane Closure
at Locust project
62 Sun Valley Dr Stuart Rd Atlas Dr 06/09/25 06/30/25 Offsite utility work for Landmark Public Works Inspections Alexander Cervantes Full Closure
at Locust project
63 Sunset St University Dr W Anna St 01/20/25 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
64 Tawakoni Dr(5908) Amistad Ln at Intersection 05/19/25 06/27/25 ADA Ramp Repair Streets Roy San Miguel Lane Closure
Trinity Rd S McKinney St E Mary Ln 06/09/25 08/29/25 Force Main Waterline being Public Works Inspections Collin Cole Full Closure
65 installed,staging area and line
install.Road closed to through
traffic
66 Sa Unicorn Lake Blvd State School Rd Wind River Ln 03/25/25 O6/30/25 nitary sewer work Private Development Gavin Petner Lane Closure
Exported on June 20,2025 11:50:23 AM CDT
Fs-t.tl I-11t.lt. From To Closure Start Closure End
Date Date Description Department Department Contact Closure Type
67 Union Cir(in entirety) Chestnut St Prairie St 05/12/25 10/01/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
68 Welch St Eagle or Hickory St 06/03/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
69 Welch St Chestnut St Mulberry St 02/03/25 07/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
70 Welch St Eagle Dr Highland St 03/13/25 07/04/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
71 Welch St Highland St Hickory St 08/26/24 07/31/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
72 Westway St Anna St Bolivar St 01/24/25 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
73 Willowwood St Westwood Dr Leslie St 03/10/25 06/27/25 Sanitary sewer,water and Private Development Gavin Petner Lane Closure
storm sewer install
Exported on June 20,2025 11:50:23 AM CDT
3 Street Closure Report: Completed Closures smartsheet
Street/Intersection From Description Department Department Contact
Bell Ave I University Dr(Hwy 380) Texas St 05/12/25 06/03/25 Waterline tap and new Atmos Drainage Christopher Yanez Full Closure
installation Engineering Private
1 Development Public Works
Inspections Streets Traffic
TXDoT Water Wastewater
2 Bell Ave N(1000) Chappel Dr Texas St 05/12/25 06/03/25 Waterline tap and new Water Christopher Yanez Full Closure
installation
3 Bernard St Lindsey St Fannin St 08/26/24 06/20/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
4 Clear River Ln Montecito or Sweet Cloud Way 04/07/25 05/23/25 Concrete Panel Repair Streets Roy San Miguel Lane Closure
5 Collins St Ave A Bernard St 08/26/24 06/20/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
6 Correll Ln University or W Amherst or 06/02/25 06/12/25 Water Taps Public Works Inspections Alexander Cervantes Lane Closure
Eastpark Blvd Linden or Crescent St 04/28/25 05/26/25 Jobsite needs to be able to Public Works Inspections Collin Cole Full Closure
7 access the buildings with
cranes but cant do that from
inside jobsite
8 Edor St Emery St University Dr 04/28/25 05/26/25 Sanitary Sewer Being installed Public Works Inspections Collin Cole Lane Closure
in the Northbound lane
9 Nautical Ln Hickory Creek Rd Ocean or 04/28/25 05/27/25 Water and Storm line tie ins Private Development Gavin Petner Lane Closure
10 North Bell Ave US 380 Administration 06/12/25 06/13/25 Atmos Main Repair Atmos Sheldon Gatewood Lane Closure
11 Panhandle St Ector St Aileen St 09/27/24 05/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
Parvin St @ Bonnie Brae St 06/09/25 06/11/25 Installation of storm drain Engineering Robin Davis Full Closure
12 infrastructure crossing Parvin-
(No access to Bonnie Brae from
Parvin)
13 Ryan Rd Creekside or Granada Trl 05/19/25 05/23/25 Sanitary Sewer improvement Public Works Inspections John Cantu Full Closure
Wastewater
14 Trinity Rd McKinney St Blagg Rd 05/05/25 06/06/25 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
Exported on June 20,2025 11:50:32 AM CDT