Public Works Information Sheet
Hickory Street Water Project (Phase 1)
1. Location: Hickory Street from Bonnie Brae Street to North Texas Boulevard
2. Proposed Date of Construction:May 1, 2017
3. Proposed Date of Completion: November 1, 2017
4. Brief Description of the Project: This is phase one of a four phase process for this
capital improvement project that will replace an eight inch water line. The existing eight inch water
line is under sized, has a high rate of failure and will be replaced by a twelve inch PVC water
line. Phase two from North Texas Boulevard to Avenue B will begin in July.
Public notification on this project includes: Door-hangers placed at impacted residences; press release,
meeting with representatives from the University of North Texas; notification letter sent to all
impacted residences and businesses; neighborhood meeting and information sent on social media.
5. Special Requirements: During this project, one lane of traffic on Hickory Street will remain
open whenever possible. No parking signs will be in place and there will be no parking on the
north side of Hickory Street. There may be temporary delays in getting in and out of driveways.
6. Funding Source: The project is budgeted at $2.4 million and is being funded by voter
approved bond funds.
7. Map: Please see attached map for Phase I.
8. Contact Information:
Name: Michael Vickery
Phone Number: 940-349-7332
E-mail: Michael.Vickery@cityofdenton.com
Hickory St CIP 2017 - Water Dept Phase I (Bonnie Brae - North Texas Blvd)
HOUSTON PL
Z HOUSTON PL
tp
Z
Z
m
HOUSTON PL F
rn CO
m v, w
A _ J
O Q
Co
W OAK ST
� I F
U)
w
Z
co
W OqK ST
Q J
0 J
W HICKORN STME
jW
Io
U)
w
J
m
Q �¢¢
coSTELLA ST w
X o
w w
z
Z r
m u-
O
cn w w z
> Q
Q
rn
CHARLOTTE ST
W SYCAMORE ST
_ Water Phase I - 6 Months (IN PROGRESS) e
Roadway
Parcels
0 250 500 1,000
IIIIIIIIIIIIIIIIIIIIiFeet
DISCLAIMER:
The City of Denton has prepared this map for departmental use.This is not an official map of the City of Denton and should not be used for legal,engineering,or surveying purposes,but rather for reference purposes only.This map is the property of the Cityof Denton,
and has been made available to the public based on the Public Information Act.The City of Denton makes every effort to produce and publish the most current and accurate information possible.No warranties,expressed or implied,are provided for the data herein,its
use or its interpretation.Utilization of this map indicates understanding and acceptance of this statement.
Hickory Street - CIP 2017
Water Department
� W.OAK•ST � 00
W ~ ~ U U O u
C7-4 cn U m 2 H
W .> H W U > LL J W W
0
�Ogi:ST tZ O Z. Z Z . Z d
'"1 m W HICKORYST � o
Z U U W
W W m
_ .Q U- Q Q W = J
U
Q I > Q U ¢ w Z
STELLAST W MULBERRY-ST m W MULBERRY.ST U
U
;W:.asteDepartment WAK ST W In m } = Jz-
U) J> H W U LLWQ W
'Oq z z O J > -FFF z o z a
Q
SS Z
'or
W HICKORY,ST 4uu)
w w w I
1
> a
> > > Q w z
STELLTAST ¢ Q W MULBERRY-ST m 77-W MULBERRY.ST
Street Department
W.OAKLL
ST co
m cn
W U) z �-
w (D U)
>
cn U W U Z
z H W > LL J W w
�Oq� m z O Q, z : d
ST z z z i
ILI HICKORYiST
1iL I
> w ; Q
`1 a LL > Q V
L 4f,
W
LLI> > > `n Q w z
Q STELLTAST Q Q W MULBERRY-ST m W MULBERRY.ST
77% 1 1 1 -Ti i i Ei�-, i 1
1 11
Start Date - January 2017 Start Date - May 2017 Start Date - August 2017 e
WW Phase I - 1 Month (COMPLETE) Water Phase I -6 Months Streets Phase I - 4 Months o o=
WW Phase 11 - 2 Months (COMPLETE) Water Phase 11 -6 Months Streets Phase 11 - 3 Months
WW Phase III - 3 Months (IN PROGRESS) Water Phase III - 3 Months Streets Phase III -3 Months
WW Phase IV -3 Months Water Phase IV -6 Months Streets Phase IV - 3 Months
WW Phase V -3 Months Streets Phase V -5 Months
WW Phase VI -3 Months
Date: 4/27/2017
Stop Date - June 2018 Stop Date - January 2019 Stop Date - January 2019
0 250 500 1,000
Total Project Time - 18 months Total Project Time - 21 months Total Project Time - 18 months 1 inch =500 feet Feet