2025/07/18 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR July 21 st - 27th
Closure Start IMI escription Department Department Contact Closure Type
Street/Intersection To Date
1 Robson Rd 1-35W Orangewood Trail 07/18/25 07/21/25 Adding right turn lanes for Hunters Ranch Public Works Inspections Gary Hatfield Lane Closure
2 Scripture St Bonnie Brae St 1-35 Service Rd 08/18/25 08/22/25 Sidewalk/ADA Repair Streets Roy San Miguel Lane Closure
Exported on July 18,2025 12:03:06 PM CDT
2 Street Closure Report: Current Closures smartsheet
�L� 02MULiRaum . . Description Department Department Contact ��Il A
17AjIeen St Panhandle St Cordell St 09/27/24 08/16/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
2St Sunset St University or(US 380) 05/27/25 08/01/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
3 Alice St Panhandle St Crescent St 05/02/25 12/05/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
4 Apollo or Redstone Rd Selene Dr 07/24/25 02/13/26 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
5 Ave A Eagle or Highland St 02/03/25 07/31/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
6 Ave B Fannin St Margie St 11/22/24 07/31/25 Pavement replacement Engineering Scott Fettig Full Closure
7 Ave D Chestnut St Mulberry St 05/12/25 08/15/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
8 Ave G Prairie St Louise St 03/13/25 07/25/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
Bonnie Brae St Conquest or Windsor or 07/07/25 07/21/25 Removing dirt along existing Engineering Jesus Perez Lane Closure
back of curb and removing
existing large trees along the
9 back of curb in the same area.
Contractor will also tie-in new
L 16-inch waterline to existing 16-
inch waterline.
Bonnie Brae St Conquest or North Lakes Park 07/07/25 08/08/25 Contractor will be demolishing Engineering Jesus Perez Full Closure
the existing street intersection
of Bonnie Brae and Riney
Road. The Contractor will
10 construct the new concrete
street intersection. Contractor
has built a temporary concrete
pavement detour to allow traffic
to keep moving north and south.
Bonnie Brae St S Willowwood St Parvin St 06/23/25 10/24/25 Installation of drainage Engineering Robin Davis Full Closure
infrastructure,embankment
11 work in advance of street
widening. (Access to Natl
Wholesale&residents only)
12 Brookside or(5700) Trailridge or @ intersection 07/21/25 08/15/25 Sidewalk Repair Streets Roy San Miguel Lane Closure
13 Cactus Cir Yucca or (End of street)Cul de sac 04/28/25 09/02/25 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
14 Carlton St Aileen St Malone St 07/23/25 09/19/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
15 Chestnut St Ave C Ave D 05/12/25 08/15/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
16 Clover Ln Robinwood Ln Glenwood Ln 11/12/24 07/31/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure
17 Congress St Ponder St Carroll Blvd 03/31/25 09/30/25 Utility installations and Engineering Megan Davidson Rolling Closure
pavement replacement
18 Congress St W Malone St Bryan St 01/31/25 07/25/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
19 Cordell St Colt St Fulton St 06/30/25 09/26/25 Full road reconstruction Engineering Megan Davidson Full Closure
20 Crescent St W Aileen St Malone St 05/21/25 09/05/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
21 Denton St Hickory St Congress St 06/02/25 11/05/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
Eagle or Ave C Ave A 03/17/25 08/29/25 Using it or an entrance due to Public Works Inspections Collin Cole Lane Closure
22 elevation changes in the jobsite
it is the only way to get into the
site
23 Ector St Cordell St University or(US380) 06/30/25 07/30/25 Sewer Line Being installed, Public Works Inspections Collin Cole Full Closure
Manholes,pipe,paving
24 Egan St Carroll Blvd Bolivar St 05/07/25 09/10/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
25 Emery St Alice St Dead End(West of Fulton) 02/03/25 08/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
26 Fry St Oak St Hickory St 04/28/25 07/25/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure
27 Fulton St Cordell St Emery St 02/03/25 08/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
Exported on July 18,2025 12:03:14 PM CDT
Streett Intersection From To Closure Start Closure End
Date Date Description Department Department Contact Closure Type
Glenwood or Kayewood or Mistywood Ln 07/21/25 07/31/25 Drainage Cut across Glenwood Drainage Sheldon Gatewood Full Closure
28 to remove and install new
Junction Box
29 Hercules Ln(East bound) Redstone Rd Stuart Rd 07/18/25 07/31/25 Offsite utility work for Landmark Public Works Inspections Alexander Cervantes Lane Closure
at Locust project
30 Hercules Ln(West bound) Redstone Rd Stuart Rd 07/21/25 08/02/25 Offsite utility work for Landmark Public Works Inspections Alexander Cervantes Lane Closure
at Locust project
31 Hickory Creek Rd Riverpass or Country Club Rd(FM 1830) 03/13/23 12/31/26 Bridge Installation Engineering Tracy Beck Full Closure
Hilltop Rd Country Club Road(FM 1830) @ intersection 05/27/25 09/30/25 Hilltop Road at Country Club Engineering Tracy Beck Full Closure
Road will be reconstructed(new
32 drainage,road,etc.)and new
northbound right turn lane will
be added to Country Club Road
33 Hobson Ln Forrestridge Dr Country Club Rd 05/08/25 07/25/25 Utility work and turn lane Public Works Inspections Gavin Petner Full Closure
construction on Hobson
34 Huisache St Aspen Dr Yucca Dr 04/09/25 08/08/25 Utilities and Pavement Engineering Dante Hale Rolling Closure
replacement
Jim Christal Rd Masch Branch Rd @ Intersection 03/07/25 08/11/25 Adding 2 Lanes E/W on Jim Public Works Inspections Kirk Winter Lane Closure
35 Christal:Adding a turn Lane on
Masch Branch
36 Juno Ln Atlas Dr Stuart Dr 04/09/25 08/08/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
37 Mistywood Ln Robinwood Ln Glenwood Ln 04/28/25 07/31/25 Voids underground Other Sheldon Gatewood Full Closure
38 Mockingbird Ln Mingo Rd University or(U.S.380) 06/16/25 08/01/25 Bore work to install new Private Development Zabdiel Mota Lane Closure
sanitary sewer line.
39 Mounts Ave Congress St W Haynes St 03/21/25 07/25/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
40 Mulberry St Welch St Bernard St 11/29/24 08/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
41 Mulberry St Elm St Carroll Blvd 03/17/25 08/01/25 Water/Wastewater connections Public Works Inspections Stephany Trammell Full Closure
42 Normal St Oak St Scripture St 05/08/25 09/05/25 Utility installations and Engineering Megan Davidson
pavement replacement.
43 Northridge St Hinkle or Bolivar St 04/16/25 04/20/26 Utilities and Pavement Engineering Dante Hale Rolling Closure
replacement
44 Oak St Carroll Blvd Fry St 04/21/25 07/25/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure
45 Oak St Welch St Ave C 04/28/25 07/25/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure
46 Oak St E(109) Austin St @ intersection 05/19/25 08/01/25 ADA/Sidewalk Work at Streets Roy San Miguel Lane Closure
Intersection
47 Ocean Dr Atlantic Dr Nautical Ln 04/14/25 07/30/25 Sanitary Sewer install Private Development Gavin Petner Full Closure
Parvin St Larkhall Ln Bonnie Brae St 07/21/25 09/05/25 Installation of Drainage Engineering Robin Davis Full Closure
Infrastructure crossing Parvin
48 near Bonnie Brae. NO
ACCESS TO BONNIE BRAE
FROM PARVIN-Use
Willowwood
49 Pershing Dr Atlas Dr Stuart Rd 05/08/25 12/15/25 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
50 Ponder Ave Oak St W Panhandle St 06/02/25 12/31/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
51 Prairie St Welch St Bernard St 03/13/25 07/25/25 Utility installations Engineering Megan Davidson Full Closure
52 Precision or Airport Rd UNIT Library Annex 04/01/25 07/31/25 Reconstruction Engineering Other Gio Pineiro Full Closure
53 Redstone Rd Hercules Ln Neptune or 05/05/25 06/12/26 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
Riney Rd Bonnie Brae St Hardaway Rd 03/08/25 08/01/25 Contractor to install 12-inch Engineering Jesus Perez Full Closure
54 waterline to provide water to the
new DISD elementary school
55 Robinwood Ln Emerson Ln Live Oak St 11/12/24 07/31/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure
56 Robinwood Ln Live Oak St Kayewood Dr 01/27/25 07/31/25 Road reconstruction(Milling Engineering Sheldon Gatewood Full Closure
and C/G Removal,Stabilization)
57 Scripture St Jagoe St Ponder St 03/04/25 10/17/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
58 Selene Dr Neptune or Stuart Rd 06/04/25 11/28/25 Engineering Scott Fettig Full Closure
59 Seven Oaks Ln(7912) Clear River Ln @ Intersection 06/23/25 08/08/25 Sidewalk Repair Streets Roy San Miguel Lane Closure
60 Sun Valley Dr Stuart Rd Atlas or 06/09/25 07/25/25 Asphalt repairs for Landmark at�Public Works Inspections Alexander Cervantes Full Closure
Locust project
Exported on July 18,2025 12:03:14 PM CDT
Streett Intersection From To Closure Start Closure End Description Department Department Contact Closure Type
Date Date 1
61 Sunnydale Ln Sun Valley Dr Kings Row 07/10/25 12/05/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
62 Sunset St Carroll Blvd Bolivar St 07/07/25 08/31/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
63 Sunset St University Dr W Carroll Blvd 01/20/25 10/16/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
Trinity Rd S McKinney St E Mary Ln 06/09/25 08/29/25 Force Main Waterline being Public Works Inspections Collin Cole Full Closure
64 installed,staging area and line
install.Road closed to through
traffic
65 Union Cir(in entirety) Chestnut St Prairie St 05/12/25 10/01/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
66 Welch St Eagle Dr Hickory St 05/31/24 10/15/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
67 Westway St Anna St Bolivar St 01/24/25 07/31/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
68 Yellowstone PI Hercules Ln Juno Ln 06/30/25 09/01/25 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
Exported on July 18,2025 12:03:14 PM CDT
3 Street Closure Report: Completed Closures smartsheet
Street/Intersection V From Description Department Department Contact
Airport Rd(FM 1515) 135 E Frontage Rd Airport/135W Frontage Rd 07/07/25 07/14/25 Construction of the new Engineering Robin Davis Full Closure
1 alignment of Bonnie Brae
connecting to Airport Road/FM
1515
2 Ave A Collins St Eagle Dr 10/08/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
3 Bernard St Lindsey St Fannin St 08/26/24 06/20/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
4 Bonnie Brae St Airport Rd(FM 1515) Walt Parker Dr(Main Stadium 01/06/25 07/14/25 Utility installations and Engineering Robin Davis Full Closure
Dr) pavement replacement.
5 Camelot St Hercules Ln Stuart Rd 04/28/25 06/27/25 Utilities and Pavement Engineering Dante Hale Rolling Closure
replacement
6 Collins St Ave A Bernard St 08/26/24 06/20/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
7 Eagle Dr Welch St @ intersection 07/17/25 07/17/25 Asphalt repair on intersection of Public Works Inspections Christopher Yanez Lane Closure
Welch and Eagle Dr Streets Traffic Water
8 Granada Trail Granada Trail Seville Rd 06/16/25 06/27/25 installing sewer pipe Wastewater John,Cantu Lane Closure
9 La Mirada(1500) Manten Blvd Zilda Way 06/09/25 07/04/25 Concrete Panel Repair Streets Roy San Miguel Lane Closure
10 Margie St Ave A Ave B 11/01/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
11 Morse St Loop 288 Mayhill Rd 12/02/24 06/20/25 Water Line Replacement and Public Works Inspections Kristine Stewart Lane Closure
Road Reconstruction Streets Water
12 Robson Ranch Rd Frontage Rd(SB) Briarwood Rd 06/20/25 06/24/25 Grading of new right turn lanes Private Development Public Gary Hatfield Lane Closure
Works Inspections Other
13 Stuart Rd Hercules Ln Kings Row 06/09/25 07/18/25 Offsite utility work for Landmark Public Works Inspections Alexander Cervantes Lane Closure
at Locust project
14 Tawakoni Dr(5908) Amistad Ln at Intersection 05/19/25 06/27/25 ADA Ramp Repair Streets Roy San Miguel Lane Closure
15 Unicorn Lake Blvd State School Rd Wind River Ln 03/25/25 06/30/25 Sanitary sewer work Private Development Gavin Petner Lane Closure
16 Willowwood St Westwood Dr Leslie St 03/10/25 06/27/25 Sanitary sewer,water and Private Development Gavin Petner Lane Closure
storm sewer install
Exported on July 18,2025 12:03:20 PM CDT