2025/07/25 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR July 28th - Aug 3rd
Street/Intersection From Closure Start
Date Description Department Department Contact Closure Type
Bonnie Brae St S Willowwood St Parvin St 09/08/25 12111121 Installation of drainage infrastructure, Engineering Robin Davis Full Closure
1 embankment work in advance of street
widening.(Access to Natl Wholesale&
residents only)
2 Kings Row Stuart Rd Valley View Rd 08/04/25 08/08/25 Utilities and Pavement replacement Engineering Dante Hale Full Closure
3 Scripture St Bonnie Brae St 1-35 Service Rd 08/18/25 08/22/25 Sidewalk/ADA Repair Streets Roy San Miguel Lane Closure
Exported on July 25,2025 12:11:43 PM CDT
2 Street Closure Report: Current Closures smartsheet
a re End Description J Department Department Contact ��Il
Aileen St Panhandle St Cordell St 09/27/24 08/16/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
Airport Road/FM 1515 135 E Service Rd 135 W Service Rd 07/30/25 08/18/25 Paving work by both City and Engineering Robin Davis Full Closure
TxDot contractors for the 35E,
2 Bonnie Brae and Airport Road
projects.(USE WESTERN
BLVD)
3 Alice St Sunset St University or(US 380) 05/27/25 08/01/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
4 Alice St Panhandle St Crescent St 05/02/25 12/05/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
5 Apollo Dr Redstone Rd Selene Dr 07/24/25 02/13/26 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
6 Ave A Eagle or Highland St 02/03/25 07/31/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
7 Ave B Fannin St Margie St 11/22/24 07/31/25 Pavement replacement Engineering Scott Fettig Full Closure
8 Ave D Chestnut St Mulberry St 05/12/25 08/15/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
9 Ave G Prairie St Louise St 03/13/25 09/01/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
Bonnie Brae St Conquest Dr North Lakes Park 07/07/25 08/08/25 Contractor will be demolishing Engineering Jesus Perez Full Closure
the existing street intersection
of Bonnie Brae and Riney
Road. The Contractor will
10 construct the new concrete
street intersection. Contractor
has built a temporary concrete
pavement detour to allow traffic
to keep moving north and south.
Bonnie Brae St S 135 E Walt Parker or 07/30/25 08/18/25 Paving work by both City and Robin Davis Full Closure
11 TxDot contractors for the 35E,
Bonnie Brae and Airport Road
projects.
12 Brookside or(5700) Trailridge or @ intersection 07/21/25 08/15/25 Sidewalk Repair Streets Roy San Miguel Lane Closure
13 Cactus Cir Yucca or (End of street)Cut de sac 04/28/25 09/02/25 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
14 Carlton St Aileen St Malone St 07/23/25 09/19/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
15 Chestnut St Ave C Ave D 05/12/25 08/15/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
16 Clover Ln Robinwood Ln Glenwood Ln 11/12/24 07/31/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure
17 Congress St Ponder St Carroll Blvd 03/31/25 09/30/25 Utility installations and Engineering Megan Davidson Rolling Closure
pavement replacement
18 Congress St W Malone St Bryan St 01/31/25 08/22/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
19 Cordell St Coit St Fulton St 06/30/25 09/26/25 Full road reconstruction Engineering Megan Davidson Full Closure
20 Crescent St W Aileen St Malone St 05/21/25 09/05/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
21 Denton St Hickory St Congress St 06/02/25 11/05/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
Eagle or Ave C Ave A 03/17/25 08/29/25 Using it or an entrance due to Public Works Inspections Collin Cole Lane Closure
22 elevation changes in the jobsite
it is the only way to get into the
site
23 Ector St Cordell St University or(US380) 06/30/25 08/30/25 Sewer Line Being installed, Public Works Inspections Collin Cole Full Closure
Manholes,pipe,paving
24 Egan St Carroll Blvd Bolivar St 05/07/25 09/10/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
25 Emery St Alice St Dead End(West of Fulton) 02/03/25 08/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
26 Fry St Oak St Hickory St 04/28/25 08/08/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure
27 Fulton St Cordell St Emery St 02/03/25 08/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
Glenwood or Kayewood or Mistywood Ln 07/21/25 08/31/25 Drainage Cut across Glenwood Drainage Sheldon Gatewood Full Closure
28 to remove and install new
Junction Box
Exported on July 25,2025 12:11:50 PM CDT
Fs-tleett ti.11 From To Closure Start Closure End
Date Date Description Department Department Contact Closure Type
29 Hercules Ln(East bound) Redstone Rd Stuart Rd 07/18/25 07/31/25 Offsite utility work for Landmark Public Works Inspections Alexander Cervantes Lane Closure
at Locust project
30 Hercules Ln(West bound) Redstone Rd Stuart Rd 07/21/25 08/02/25 Offsite utility work for Landmark Public Works Inspections Alexander Cervantes Lane Closure
at Locust project
31 Hickory Creek Rd Riverpass Dr Country Club Rd(FM 1830) 03/13/23 12/31/26 Bridge Installation Engineering Tracy Beck Full Closure
Hilltop Rd Country Club Road(FM 1830) @ intersection 05/27/25 09/30/25 Hilltop Road at Country Club Engineering I Tracy Beck Full Closure
Road will be reconstructed(new
32 drainage,road,etc.)and new
northbound right turn lane will
be added to Country Club Road
33 Huisache St Aspen or Yucca Dr 04/09/25 09/05/25 Utilities and Pavement Engineering Dante Hale Rolling Closure
replacement
Jim Christal Rd Masch Branch Rd @ Intersection 03/07/25 08/11/25 Adding 2 Lanes E/W on Jim Public Works Inspections Kirk Winter Lane Closure
34 Christal:Adding a turn Lane on
Masch Branch
35 Juno Ln Atlas Dr Stuart Dr 04/09/25 09/12/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
36 Mistywood Ln Robinwood Ln Glenwood Ln 04/28/25 08/31/25 Voids underground Other Sheldon Gatewood Full Closure
37 Mockingbird Ln Mingo Rd University Dr(U.S.380) 06/16/25 08/01/25 Bore work to install new Private Development Zabdiel Mote Lane Closure
sanitary sewer line.
38 Mounts Ave Congress St W Haynes St 08/01/25 11/01/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement
39 Mulberry St Welch St Bernard St 11/29/24 08/01/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
40 Mulberry St Elm St Carroll Blvd 03/17/25 08/01/25 WaterM/astewater connections Public Works Inspections Stephany Trammell Full Closure
41 Normal St Oak St Scripture St 05/08/25 09/05/25 Utility installations and Engineering Megan Davidson
pavement replacement.
42 Northridge St Hinkle or Bolivar St 04/16/25 04/20/26 Utilities and Pavement Engineering Dante Hale Rolling Closure
replacement
43 Oak St Carroll Blvd Fry St 04/21/25 08/08/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure
44 Oak St Welch St Ave C 04/28/25 08/08/25 Mastec relocating gas lines Public Works Inspections Stephany Trammell Rolling Closure
45 Oak St E(109) Austin St @ intersection 05/19/25 08/01/25 ADA/Sidewalk Work at Streets Roy San Miguel Lane Closure
Intersection
46 Ocean or Atlantic Dr Nautical Ln 04/14/25 07/30/25 Sanitary Sewer install Private Development Gavin Petner Full Closure
Parvin St Larkhall Ln Bonnie Brae St 07/21/25 09/05/25 Installation of Drainage Engineering Robin Davis Full Closure
Infrastructure crossing Parvin
47 near Bonnie Brae. NO
ACCESS TO BONNIE BRAE
FROM PARVIN-Use
Willowwood
48 Pershing Dr Atlas Dr Stuart Rd 05/08/25 12/15/25 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
49 Ponder Ave Oak St W Panhandle St 06/02/25 12/31/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
50 Precision or Airport Rd UNIT Library Annex 04/01/25 07/31/25 Reconstruction Engineering Other Gio Pineiro Full Closure
51 Redstone Rd Hercules Ln Neptune Or 05/05/25 06/12/26 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
Riney Rd Bonnie Brae St Hardaway Rd 03/08/25 08/01/25 Contractor to install 12-inch Engineering Jesus Perez Full Closure
52 waterline to provide water to the
new DISD elementary school
53 Robinwood Ln Emerson Ln Live Oak St 11/12/24 08/31/25 Full Road Reconstruction Engineering Sheldon Gatewood Full Closure
54 Robinwood Ln Live Oak St Kayewood or 01/27/25 08/31/25 Road reconstruction(Milling Engineering Sheldon Gatewood Full Closure
and C/G Removal,Stabilization)
55 Scripture St Jagoe St Ponder St 03/04/25 10/17/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
56 Selene Dr Neptune Dr Stuart Rd 06/04/25 11/28/25 Engineering Scott Fettig Full Closure
57 Seven Oaks Ln(7912) Clear River Ln @ Intersection 06/23/25 08/08/25 Sidewalk Repair Streets Roy San Miguel Lane Closure
58 Sunnydale Ln Sun Valley Dr Kings Row 07/10/25 12/05/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
59 Sunset St Carroll Blvd Bolivar St 07/07/25 08/31/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
60 Sunset St University Dr W Carroll Blvd 01/20/25 10/16/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
Exported on July 25,2025 12:11:50 PM CDT
Streett Intersection To Closure Start Closure End —[Dep.rtment Contact Closure Type
Date Date Description Department
Trinity Rd S McKinney St E Mary Ln 06/09/25 08/29/25 Force Main Waterline being Public Works Inspections Collin Cole Full Closure
61 installed,staging area and line
install.Road closed to through
traffic
62 Unicorn Lake Blvd State School Rd Shoreline Dr 07/03/25 07/30/25 Sanitary sewer connection and Private Development Gavin Petner Lane Closure
paving repair
63 Union Cir(in entirety) Chestnut St Prairie St 05/12/25 10/01/25 Utility installations and Engineering Megan Davidson Full Closure
pavement replacement.
64 Welch St Eagle or Hickory St 05/31/24 10/15/25 Utility installations and Engineering Scott Fettig Rolling Closure
pavement replacement.
65 Westway St Anna St Bolivar St 01/24/25 07/31/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
66 Yellowstone PI Hercules Ln Juno Ln 06/30/25 09/01/25 Utilities and Pavement Engineering Dante Hale Full Closure
replacement
Exported on July 25,2025 12:11:50 PM CDT
3 Street Closure Report: Completed Closures smartsheet
Street/Intersection V From Description Department Department Contact
Airport Rd(FM 1515) 135 E Frontage Rd Airport/135W Frontage Rd 07/07/25 07/14/25 Construction of the new Engineering Robin Davis Full Closure
1 alignment of Bonnie Brae
connecting to Airport Road/FM
1515
2 Ave A Collins St Eagle Dr 10/08/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
3 Bonnie Brae St Airport Rd(FM 1515) Walt Parker Dr(Main Stadium 01/06/25 07/14/25 Utility installations and Engineering Robin Davis Full Closure
Dr) pavement replacement.
Bonnie Brae St Conquest Dr Windsor Dr 07/07/25 07/21/25 Removing dirt along existing Engineering Jesus Perez Lane Closure
back of curb and removing
existing 4 back of cub trees along in a the me are a.
Contractor will also tie-in new
16-inch waterline to existing 16-
inch waterline.
5 Camelot St Hercules Ln Stuart Rd 04/28/25 06/27/25 Utilities and Pavement Engineering Dante Hale Rolling Closure
replacement
6 Eagle Dr Welch St @ intersection 07/17/25 07/17/25 Asphalt repair on intersection of Public Works Inspections Christopher Yanez Lane Closure
Welch and Eagle or Streets Traffic Water
7 Granada Trail Granada Trail Seville Rd 06/16/25 06/27/25 installing sewer pipe Wastewater John,Cantu Lane Closure
8 Hobson Ln Forrestridge or Country Club Rd 05/08/25 07/25/25 Utility work and turn lane Public Works Inspections Gavin Petner Full Closure
construction on Hobson
9 La Mirada(1500) Manten Blvd Zilda Way 06/09/25 07/04/25 Concrete Panel Repair Streets Roy San Miguel Lane Closure
10 Margie St Ave A Ave B 11/01/24 06/30/25 Utility installations and Engineering Scott Fettig Full Closure
pavement replacement.
11 Prairie St Welch St Bernard St 03/13/25 07/25/25 Utility installations Engineering Megan Davidson Full Closure
12 Robson Rd 1-35W Orangewood Trail 07/18/25 07/21/25 Adding right turn lanes for Public Works Inspections Gary Hatfield Lane Closure
Hunter's Ranch
13 Stuart Rd Hercules Ln Kings Row 06/09/25 07/18/25 Offsite utility work for Landmark Public Works Inspections Alexander Cervantes Lane Closure
at Locust project
14 Sun Valley Dr Stuart Rd Atlas or 06/09/25 07/25/25 Asphalt repairs for Landmark at Public Works Inspections Alexander Cervantes Full Closure
Locust project
15 Tawakoni Dr(5908) Amistad Ln at Intersection 05/19/25 06/27/25 ADA Ramp Repair Streets Roy San Miguel Lane Closure
16 Unicorn Lake Blvd State School Rd Wind River Ln 03/25/25 06/30/25 Sanitary sewer work Private Development Gavin Petner Lane Closure
17 Willowwood St Westwood or Leslie St 03/10/25 06/27/25 Sanitary sewer,water and Private Development Gavin Petner Lane Closure
storm sewer install