1987-2170923L AN ORDINANCE AUTHORIZING THE EXECUTION OF A CHANG5 ORDER TO A CONTRACT BETWEEN THE CITY OF DENTON AND TONTO CONSTRUCTION, INC , AND PROVIDING AN EFFECTIVE DATE WHEREAS, on February 17, 1987, the City awarded a contract for the construction of certain improvements to the Water Treatment Plant Upgrade Phase II, Bid No 9657, and WHEREAS, the C~ty Manager having recommended to the Council that a change order be authorized to amend such contract and said change order being ~n compliance with the requirements of art 2368a, V A C S , NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF DENTON SECTION I That the change order to the contract between the C~ty and Tonto Construction, Inc ~n the amount of Twenty-n~ne Thousand Eight Hundred and Two Dollars and Fourteen Cents ($29,802 14) is hereby approved and the expenditure of funds therefor ~s hereby authorized SECTION II That this ordinance shall become effective ~mmedlately upon ~ts passage and approval PASSED AND APPROVED thls the 1st day of December, 1987 ATTEST CITY SECa .TARY APPROVED AS TO LEGAL FORM DEBRA ADAMI DRAYOVITCHt CITY ATTORNEY DATE December 1, 1987 CITY COUtlCIL REPORT TO. Mayor and Members of the City Council FROM Lloyd V Harrell, City Manager SUBJECT CHANGE ORDER #6 TONTO CONSTRUCTION~ INC RECOI~IEtlDATIOtt We recommend this Change Order l/6 in the amount of $29~802 iQ to Tont~) Construction, Inc be approved .~UI~RY This change order Involves the replacement of a caustic soda tank in conjunction with the Denton Water Treatment Plant upgrade The Public Utlhty Advisory Board has approved this change order ..B/tCi(GROU~ID Memo o! December 1, 1987 Proposal from Tonto Construction _PROGRAI~ DE?ARTNENTS OR GROUPS AFFECTED Water Treatment P/ant Upgrade Phase I! _FISCAL H1PACT 1987/88 Water Utility Bond Funds Account tt 623-008-0/~60-9t01 Respee. x~l ly submttted Lloyd V Harrell // City Manager Prepared by Tom s ,w, c P TI t-I e Assistant Purchasing Agent Approved ~T~ t]a. Purchasing Agent Dec~ ')er 1, 1987 CITY COUNCIL AGENDA ITEM TO CHAIRMAN AND MEMBERS OF THE PUBLIC UTILITIES BOARD FROM R E Nelson, Executive Director of Utilities SUB3ECT CFtANGE ORDER t1~- (Caustic Tank-TONTO CONSTRUCTION INC ) WATER TREATMENT PLANT RECOMMENDATION The Public Utilities Board, st their meeting of November 18, 1987, recommended Lo the City Council approval of the attached change order #6 concerning replacement of e caustic tank in conjunction with Phase II Upgrade of the Denton Water Treatment Plant Project in the amount of $29,802 SUMMARY~ The existing fiberglass sodium hydroxide tank has been seriously leaking after several attempts at repairs by the tank manufacturer The existing tank needs to be replaced by a polyethylene tank of the same size and capacity as soon as possible BACKGROUND In 1981~ a fiberglass tank was installed at the Water Treatment Plant for the purpose of changing over to liquid sodium hydroxide (caustic) for adjusting the Ph of water In the treatment process Since that tlme~ the fiberglass tank has been subjected to this highly corrosive chemical and has not withstood the deterioration even after several repairs were made by the tank manufacturer Since that time, the water treatment Industry has developed a more chemically Inert tank using polyethylene Polyethylene does not react with sodium hydroxide and has been found to be highly suitable for containing this highly corrosive chemical The Utilities Staff needs to get this unsatisfactory tank replaced at this time by Tonto Construction Company as a part of the Water Treatment Plant Phase II upgrade contract This tank is in danger of rupture which could result In a possible shutdown of the Water Treatment Plant 5168U 9 Pegs 2 A second tank of polyethylene material has recently been Installed by Tonto Construction Company as part of this project However~ the Utilities Staff thought that the existing hber§iass tank could be salvaged by further repairs which has proven not to be the case PROGRAMS~ DEPARTMENTS OR GROUPS AFFECTED City of Denton, Denton Municipal Utiiltles~ Engineers and Contractors, and the c,tlzens FISCAL IMPACTi Previous Contract Amount $3,618,309 27 Net increase in contract ami ! for tank $29t802 l~ Revised Contract Amount $3,648,111 41 Net change in contract t,me of completion- no change R~l/pect fully submitted, City Manager Prepared & Approved by~ TR E Nelson, Executive Director Department of Utilit,es Exhibit I Change Order tt6 Minutes PUB Meeting of ll/18/87 5168U~9-10 TC 114-042 October 14, 1987 Nr C David Ham, P E Director of Water & Wastewater Utilities Service Center/Warehouse 901-A Texas Street Denton, Texas 76201 RE Denton Water Treatment Plant Upgrade - Phase II SUBSECT Change Order No 6 (Caustic Tank) Dear Hr Ham Please find attached five (5) copies of Change Order No 6 regarding the new caustic tank additions for your executzon Please return a fully executed copy to us upon your approval Sincerely, TONTO CONSTRUCTION, Glenn A Landry ~ Vice Preszdent GA/rmo Enclosure 2417 WEST PARK ROW · SUITE 200 · ARUNOTON TEXAS 78013 · PHONE (817) 4~0 0866 · METRO 461 6833 PROJKCT Denton water Treataent Plant Upgrade - Phase 2 CONTRACT No 9657 OWNKR Czt7 o£ Denton, Texas CONTRACTOR= Torito ConstructLon Co CHANGE ORDER NO SLx (6) DATE October 6, 1987 CHAJIQS OR ~XTRA WORK TO BE PERFOR2~D Contractor to replace the existing /lberglass sodium hydroxide tank wzth a polyethylene tank gE the sams s~ze and capacity as speciE,ed ~n Section 11234 of the Contract Speczf~catzons The tank is to be · nsulated, heat traced and ~s to meet all other provis~ons of the contract dra#~ngs The tank ia to be provLded wLth appurtenances of the same size and location as the tank which Ls to be replaced The contractor is to ensure that the heat tracing on the new tank Ls compatible with existLng cLrcu~t breakers and w~r~ng which wan provided for energL~zing the heat tracLng on the ex~st~ng tan~ or w~ll make revls~ons as necessary to accommodate the new tank The ex~st~ng tank is to be relocated to the Czt¥ of Denton Waste~ater Treatment Plant and be set Ln the storage yard located near the pole barn Amount to be Added $ 29,802 14 The compensation agreed u~on in ~hls Chan~e or SxCrs Work Order ~s a full. tom,lace and f~nal ~eYmen= £or all costs Che Con~rac~or may ~ncur as a resul~ of or relating ~o ~h~s change whether sa~d costs are known. unknown, foreseen or unforeeen a~ Chis ~me. ~nclud~ng w~=hout llm~aclon, any c~s~ for del~y, ex~ended overhead, r~la or ~mpac~ cos=. or any other effect on chan~ed or unchanged work as a result of =h~s change or Sxcra Work Order PrevLous Contract A~ount $ 3 618 30 ,.t Revxaed Contract A~ount $ 3.648.111 41 Net Change In Contract T~aa of Co~pletlon No Change ~av~sed contract tiaa o£ complet=on June 2~1988 FREESE AND NICHOLS, By ~ By EXCERPT FROM MINUTES PUBLIC UTILITIES BOARD November 18, 1987 CHANGE ORDER #6 - (CAUSTIC TANK~ TONTO CONSTRUCTION INC ) WATER TREATMENT PLANT (Sam) Ham introduced this item stating that the existing fiberglass sodium hydroxide tank has been seriously leaking after several attempts at repairs by the tank manufacturer The existing tank needs to be replaced by a polyethylene tank of the same size and capacity as soon as possible Previous Contract Amount $3,618,309 27 Net increase in contract amt 1 for tank $29,802 14 Revised Contract Amount $3,648,111 41 Net change in contract time of completion- no change LaForte made a motion that the Board recommend approval to the City Council for change order %6 in the amount of $29,802 14 Second by Thompson All ayes, no nays, motion carried EXHIBIT_,