2018-057 Engineering Contract NegotiationsDate: May 11, 2018 Report No. 2018-057 INFORMAL STAFF REPORT TO MAYOR AND CITY COUNCIL SUBJECT: At the May 8, 2018, City Council meeting, questions were asked regarding the methodology on how staff evaluates the fees for design and engineering consultants. The following provides a background on the City’s contract negotiations for professional engineering services. BACKGROUND: Contract negotiations are a critical component to project delivery. It sets the tone for the project and the expectations of both parties. The general process begins with a face to face meeting with the consultant to discuss the project limits and scope. A discussion of expectations follows, along with any questions to clarify the project’s intent. Next, the consultant responds to the scoping meeting by doing some preliminary investigation into the project and the expectations of the City to determine how much time and effort the consultant estimates is needed to complete the project including project basics as follows: 1. Topographic and Boundary Surveys – Determine all elevation challenges and legal boundaries for property acquisitions required to complete the project (easements, right of entry, right of way, etc.) 2. Geotechnical Exploration – determine all soils and their bearing capacity to design pavement thicknesses, embedment of utilities, etc. 3. Subsurface Utility Exploration – find all utilities (franchise and public) that reside within the project limits. 4. Professional design services – includes the actual design of the improvements and generation of either a study or construction documents. 5. Bid Document Creation – generate all specifications and bid documents required to let the project for construction, if warranted. 6. Construction Phase Assistance – Services here range from reviewing material submittals and quantities submitting by the contractor for pay, to taking a more active owner’s representative role onsite. Based on the scoping meeting, the consultant will determine how much time and how many people will be required to complete the project. This generally is summarized in a Level of Effort (LOE) matrix that defines all man hours and associated cost for each task in the project. A rough draft contract scope and LOE is submitted to the City’s project manager for review as to veracity of the efforts and costs anticipated. Many times staff reviews the LOE and scope to find either tasks not needed, or an excess of time built in to the LOE to accommodate a very conservative estimate on Date: May 11, 2018 Report No. 2018-057 the time required to complete the project. A primary reason for this is the consultants’ effort to try and assume that all potential project roadblocks are not known and they might need to have sufficient time built into the contract to work these issues as they arise without delay due to a contract amendment. Staff frequently reviews professional services contracts and questions how much time is really applicable to the project. This process allows staff to ensure that the City is getting the best value from our design consultants, while ensuring that both are on the same page about the expectations of the project. If staff cannot negotiate a contract to satisfaction, staff will terminate negotiations and move to negotiate with the next most qualified consultant(s) until a reasonable rate for services is reached. Attached is an example of a rate sheet and man hour breakdown by Teague, Nall, and Perkins for the City Owned Parking Lot design contract that was approved by City Council on May 8, 2018. ATTACHMENT(S): 2018 Parking Lots 2018 Parking Manhours STAFF CONTACT: Mario Canizares Assistant City Manager (940) 349-8535 Mario.Canizares@cityofdenton.com 1 ATTACHMENT ‘C’ TEAGUE NALL AND PERKINS, INC. Hourly Billing Rates by Employee Type Effective January 1, 2018 to December 31, 2018* Engineering /Landscape Architecture/ROW Hourly Billing Rate Principal $230 Team Leader $210 Senior Project Manager $200 Project Manager $170 Senior Engineer $220 Project Engineer $150 Engineer III/IV $120 Engineer I/II $100 Landscape Architect / Planner $125 Landscape Designer $100 Senior Designer $135 Designer $120 Senior CAD Technician $110 CAD Technician $90 IT Consultant $150 Clerical $60 Construction Inspector II $90 Construction Inspector III $105 Senior Construction Inspector $120 Construction Superintendent $170 ROW Manager $150 Senior ROW Agent $130 ROW Agent $110 Relocation Agent $120 Senior Utility Coordinator $130 Utility Coordinator $120 Intern $60 Surveying Survey Manager $210 Registered Professional Land Surveyor (RPLS) $170 Field Coordinator $120 S.I.T. or Senior Survey Technician $110 Survey Technician $95 1-Person Field Crew w/Equipment** $125 2-Person Field Crew w/Equipment** $160 3-Person Field Crew w/Equipment** $180 4-Person Field Crew w/Equipment** $200 Flagger $40 Abstractor (Property Deed Research) $85 Subsurface Utility Engineering (SUE) SUE Project Manager $185 SUE Engineer $160 Sr. Utility Location Specialist $100 Utility Location Specialist $85 1-Person Designator Crew w/Equipment*** $120 2-Person Designator Crew w/Equipment*** $145 2-Person Vac Excavator Crew w/Equip (Exposing Utility Only) $250 (4 hr. min) 2-Person Vac Excavator Crew w/Equip for QL-A **** $450 (4 hr. min.) Core Drill (equipment only) $750 per day All subcontracted and outsourced services shall be billed at rates comparable to TNP’s billing rates above or cost times a multiplier of 1.10. * Rates shown are for calendar year 2018 and are subject to change in subsequent years. ** Survey equipment may include truck, ATV, Robotic Total Station, GPS Units and Digital Level. *** Includes crew labor, vehicle costs, and field supplies. **** Rate applies to Quality Level A (QL-A) test holes on utilities that were designated by TNP as QL-B. 2 ATTACHMENT ‘C’ TEAGUE NALL AND PERKINS, INC. Reimbursed Direct Cost Items Effective January 1, 2018 to December 31, 2018* Direct Cost Reimbursables Photocopies: $0.154/sf letter, legal and 11” x 17” size bond paper, B&W $0.7701/sf letter, legal and 11” x 17” bond paper, color Prints: $0.154/sf letter, legal and 11” x 17” bond paper, B&W $0.7701/sf letter, legal and 11” x 17” bond paper, color Plots: $0.154/sf letter, legal and 11” x 17” bond paper, B&W $0.7701/sf letter, legal and 11” x 17” bond paper, color $0.50/sf 22” x 34” and larger bond paper or vellum, B&W $1.00/sf 22” x 34” and larger mylar or acetate, B&W Mileage $0.545/mile Plans on CD $20/each Denton 2018 Parking LotsBUDGET ESTIMATE TNP No. Prin Senior PM PE Engineer III Cad LA Clerical Reimb Total Total USE Service Center Conceptual Parking Study 26,550$ $26,600 Meeting to ID future plans 2 4 1,260$ Research 2 8 2,060$ Meetings with staff 4 8 2,520$ Option sketches 1 20 32 7,750$ Review meeting 2 4 1,260$ Draft site layout 6 20 3,400$ Aerial Photgraphy 2,000$ 2,000$ Report 2 8 2,060$ Revisions 4 8 1,680$ Final site layout 4 16 2,560$ Denia Rec Center 17,850$ $17,900 Cover 1 4 560$ General Notes, Typical Sections 2 6 940$ Demo plans 1"=20' 1 sht 3 4 8 1,760$ Parking Layout 1 sht 2 16 6 2,700$ Grading Plan 1 sht 4 16 6 3,100$ Dumpster Enclosure 8 8 2,320$ Details 6 5 10 2,650$ Quantities, Specs, Bid Docs, Estimates 8 2 1,780$ QA\QC 2 2 1 1,010$ Project Management 1 4 1,030$ 4,950$ $5,000 Landscape Plan 1 4 16 3,040$ Irrigation Plan 1 1 12 1,910$ Civic Center 36,680$ $36,750 Cover 1 4 560$ General Notes, Typical Sections 2 6 940$ Demo plans 1"=20' 2 sht 10 12 12 4,400$ Parking Layout 2 sht 6 32 12 5,800$ Grading Plan 2 sht 12 32 12 7,000$ Phasing Plan (3 shts)15 30 5,700$ Details 10 6 16 4,100$ Quantities, Specs, Bid Docs, Estimates 12 10 3,300$ TDLR Submittal 2 1,200$ 1,600$ QA\QC 4 2 2 1,620$ Project Management 2 6 1,660$ Landscape Plan 2 4 24 4,240$ 7,100$ $7,100 Irrigation Plan 2 1 18 2,860$ City Hall East 41,470$ $41,500 Cover 1 4 560$ General Notes, Typical Sections 2 6 940$ Demo plans 1"=20' 2 sht 8 12 12 4,000$ Parking Layout 2 sht 8 32 12 6,200$ Grading Plan 2 sht 12 30 12 6,780$ Details 12 10 16 4,940$ Storm Drain 8 24 10 5,140$ Retaining Wall 12 8 12 4,360$ Accessible Ramps 6 8 1,920$ Quantities, Specs, Bid Docs, Estimates 12 8 3,120$ QA\QC 4 2 2 1,620$ Project Management 3 6 1,890$ Landscape Plan 4 3 20 3,930$ 6,240$ $6,200 Irrigation Plan 3 1 12 2,310$ McKinney Street 50,220$ $50,200 Cover 1 4 560$ General Notes, Typical Sections 2 6 940$ Preliminary Layout 2 20 15 5,810$ Demo plans 1"=20' 1 sht 4 8 12 2,760$ Parking Layout 1 sht 12 24 30 7,740$ Grading Plan 1 sht 12 32 12 7,000$ Drainage Area Map 12 12 12 4,800$ On-Site Storm Drain Calcs & Plans 10 16 16 5,200$ Details 12 16 12 5,240$ Quantities, Specs, Bid Docs, Estimates 12 8 3,120$ TDLR Submittal 2 1,200$ 1,600$ QA\QC 3 4 2 1,790$ Project Management 2 16 3,660$ Lighting Plan 4 9,000$ 9,800$ Landscape Plan 1 8 30 5,630$ 9,640$ $9,650 Irrigation Plan 4 1 24 4,010$ Service Center - North Parking 20,570$ $20,600 Cover 1 4 560$ General Notes, Typical Sections 2 6 940$ Demo plans 1"=20' 1 sht 6 6 14 3,120$ Parking Layout 1 sht 3 16 4 2,720$ Grading Plan 1 sht 6 18 10 4,080$ Details 6 4 10 2,540$ Quantities, Specs, Bid Docs, Estimates 8 4 1,960$ TDLR Submittal 2 1,200$ 1,600$ QA\QC 3 2 2 1,390$ Project Management 2 6 1,660$ -$ Landscape Plan 2 2 16 2,820$ 5,830$ $5,800 Irrigation Plan 4 1 16 3,010$ Service Center - West Main Parking 31,830$ $31,800 Cover 1 4 560$ General Notes, Typical Sections 2 6 940$ Demo plans 1"=20' 2 sht 10 12 12 4,400$ Parking Layout 2 sht 12 32 12 7,000$ Grading Plan 2 sht 14 32 14 7,580$ Details 12 8 16 4,720$ Storm Drain -$ Quantities, Specs, Bid Docs, Estimates 12 8 3,120$ QA\QC 4 2 2 1,620$ Project Management 3 6 1,890$ Service Center - West Boundary Parking 18,230$ $18,200 Cover 1 4 560$ General Notes, Typical Sections 2 6 940$ Demo plans 1"=20' 1 sht 5 10 12 3,180$ Parking Layout 1 sht 4 12 6 2,660$ Grading Plan 1 sht 6 16 8 3,680$ Details 6 8 10 2,980$ Quantities, Specs, Bid Docs, Estimates 8 4 1,960$ QA\QC 2 2 1 1,010$ Project Management 2 4 1,260$ Service Center - South of Texas Street Parking 18,920$ $18,900 Cover 1 4 560$ General Notes, Typical Sections 2 6 940$ Demo plans 1"=20' 1 sht 5 8 12 2,960$ Parking Layout 1 sht 4 12 8 2,840$ Grading Plan 1 sht 8 16 6 3,900$ Details 6 8 12 3,160$ Quantities, Specs, Bid Docs, Estimates 8 6 2,140$ QA\QC 2 2 2 1,160$ Project Management 2 4 1,260$ Landscape Plan 2 4 16 3,240$ 5,550$ $5,600 Irrigation Plan 3 1 12 2,310$ SUBTOTAL Hours 56 616 14 607 -$ 311,430$ 301,630$ $301,800 April 24, 2018 Senior Cad Tech LA Designer