2019-021 American Legion Hall Design and Construction UpdateDate: February 1, 2019 Report No. 2019-021 INFORMAL STAFF REPORT TO MAYOR AND CITY COUNCIL SUBJECT: American Legion Hall design and construction update. BACKGROUND: The American Legion Hall Senior Center, located at 629 Lakey Street, is a busy recreational facility used for active senior adult programing such as sewing, educational seminars, exercise, table games, fellowship, and monthly socials. The facility has two structures, the south side built in 1957 (2,500 square feet) and the north side (2,600 square feet) built in 2003, which is connected by a covered walkway. The buildings serve as a social and recreational gathering place for adults age 50 and older. In the summer of 2017, the Parks and Recreation Department provided a tour of this facility to the City Manager. During the tour, it was noticed that several areas of the south structure built in the late 1950s had cracks in the wall and showed signs of foundation settling. The north structure had no structural issues. As a result, an engineering study was commissioned by Eikon Consulting to determine the stability of the structure, provide a repair estimate, or a replacement estimate if the repairs were too costly. Based on the age of the building, Eikon recommended that the cost to repair was not worth the effort and a full replacement of the south structure was recommended. The firm initially estimated that $614,712 was needed to replace the structure like for like with the same square footage as the current structure. This information was presented to the City Council during the Facilities Management Budget Work Session. As a result of this information, $614,712 has been budgeted in the FY 2017/18 budget for the design and construction of a new structure. In late 2017, Eikon Consulting was selected as the architectural firm for the project. Their initial design fee was $64,220 which allowed $550,462 for construction. As part of the project scope, Eikon conducted community meetings of the users and engaged City staff on the programming elements for the facility to determine the appropriate design. Based on this feedback, Eikon has recommended that the two stand-alone structures be merged into a single larger facility to approximately 7,100 square feet. This would allow the spaces to be better utilized and become more versatile by accommodating larger events, subdividing for smaller events, keeping patrons indoors, and providing a better flow throughout the building. As a result of combining the spaces, the north building would need renovation and upgrades to current safety code requirements, which were not scoped as part of the original project budget. Date: February 1, 2019 Report No. 2019-021 Gary Packan presented the design and funding to City Council on June 5, 2018. With the selected add alternates Eikon’s estimated probable cost to merge the two buildings and make the required renovations was projected at $1,100,050. Original Expenses Amount Original project scope: $ 614,712 Eikon design Fee: $ 64,220 Add revised scope: $ 243,038 Add alternates $ 67,500 Furniture, fixtures, equip. $ 75,000 Eikon design increase: $ 35,580 Total for revised project $1,100,050 Original Funding Amount Original project funding $ 614,712 Parks Gas Fund $ 100,000 Parks Bond Interest $ 153,000 Parks 915/916 Funds $ 249,838 Total funding $1,117,550 DISCUSSION: Over the course of the last six months, Eikon has been working on the completion of construction drawings. The initial budget amount of $1,100,050 from April 2018 was included in the June 2018 presentation. Since the conclusion of the construction drawings, a total of three estimates have been completed. These estimates ranged from $1,446,426 to $1,955,299. At this time, Eikon feels that the high estimate is a potential outliner. During the process of evaluating and comparing all estimates, staff found that “soft costs” such as insurance, builder mark-up, testing, permits, and a contingency were not included in the original estimate provided by Eikon. These costs are approximately $300,000-400,000. Eikon, along with staff, have identified potential value engineering, deductive alternatives for the bid as well as possible work that could be completed and/or managed by staff to help contain the costs. These items include removing the loggia, decreasing the multipurpose/storage room, and substituting building materials to help get the project closer to an acceptable construction total. CONCLUSION: Currently, $1,117,550 in cash funding has been identified for this project. If needed, an additional $307,424 is available from a combination Park Dedication (915) and Development (916) Funds to be utilized for this project. The final construction documents have been completed. The project will be put out for bid using the Request for Proposal (RFP) process. This will provide a more accurate range of costs for the Date: February 1, 2019 Report No. 2019-021 project. The results of the bid will be presented to Council with options to move forward in early March. STAFF CONTACT: Caroline Seward Program Area Manager, Parks and Recreation (940) 349-8271 Caroline.Seward@cityofdenton.com