2021-083 Summary of the September 24 Bond Oversight Committee meetingDate: October 1, 2021 Report No. 2021-083       INFORMAL STAFF REPORT TO MAYOR AND CITY COUNCIL SUBJECT: Summary of the Bond Oversight Committee meeting held on September 24, 2021. BACKGROUND: The purpose of this report is to provide the City Council with a summary of the Bond Oversight Committee meeting held on September 24, 2021 to review and discuss General Obligation (GO) funded projects which include projects from the 2012, 2014, and 2019 bond programs. DISCUSSION: Staff presented the status of capital improvement projects, revised project costs, and funding updates. Additionally, updates regarding CIP project management and process improvement was shared. The action item of the committee was the reallocation of $2,489,000 2014 GO bonds to fund the revised project scope of the Westgate Street Reconstruction endorsed by Council on August 10, 2021. The reallocation was discussed and approved by the committee. Finally, Staff presented two management reports regarding timeline updates to the bond issuance schedule and an adjustment to the transportation facility reallocation on the opinion of bond counsel. Staff is currently scheduled to provide a bond program update to City Council on October 19, 2021. The Bond Oversight Committee agenda information sheet attached provides a status update on open projects and those that have been completed as of September 2021. Please do not hesitate to contact me if you have any questions regarding the recent Bond Oversight Committee meeting. ATTACHMENTS: Bond Oversight Committee Agenda Information Sheet STAFF CONTACT: Cassey Ogden, Finance Director 940-349-7195 Cassandra.Ogden@cityofdenton.com City of Denton _____________________________________________________________________________________ AGENDA INFORMATION SHEET DEPARTMENT: Finance Department ACM: David Gaines DATE: September 24, 2021 SUBJECT Receive a report, hold a discussion, and give staff direction regarding 2012, 2014, and 2019 General Obligation (GO) funded capital projects. BACKGROUND The purpose of this item is to review the status of voter approved General Obligation (GO) funded projects, discuss the current allocation of project funds, and provide estimated completion costs for projects. Staff has included projects to update the committee on the items that have been completed and remain open as of 2021. Staff has provided a detailed spreadsheet (Exhibit 2) which provides a reconciliation of all current GO funded projects and recommended funding sources to meet estimated completion costs. Staff will discuss this spreadsheet in detail with the Committee. Below is status update on each of the GO funded projects included in Exhibit 2: 2012 Bond Election: 1. Street Reconstruction The original intent of this project was for the reconstruction of City streets with an Overall Condition Index (OCI) rating of 40 or less. Staff believed that 216 street segments representing approximately 68.15 lane miles could be completed within the 6-7 years with bonds issued over a 5-year period. To- date, 179 segments have been completed representing approximately 56.74 lane miles. Staff believes that the remaining 31 segments will be completed by the fourth quarter of 2022. In order to complete the 2012 Street reconstruction projects, an additional $2,797,737 was sold in the 2018A Certificates of Obligation (COs) issuance which occurred in August 2018. Council was presented an update regarding construction cost inflation and budget increases which resulted in the inclusion of $8,900,000 issuance of COs in the FY 2020-2021 budget. Staff has developed a plan to select contractors and construct remaining segments from the 2012 Street Reconstruction Bond by December 2022. City Hall 215 E. McKinney Street Denton, Texas www.cityofdenton.com 2. Public Art Transportation The City issued $400,000 in bonds for public art related to transportation projects. Of this amount, $97,612 was spent to install medallions at the North Texas Boulevard underpass on I-35. The Public Art Committee (PAC) initially proposed four medallions to be installed on the exterior corners of the Loop 288/I-35 bridge. TXDOT final design at this location only provided sufficient surface mounting for one medallion, leading the PAC to consider three new alternatives for the remaining funds. The first option was the installation of two pedestal medallions at the Loop 288 intersection associated with planned improvements of I-35 as presented at the Public Art Committee (PAC) at the February 7th, 2019 meeting. The second option was the potential co-location of several public art pieces with entryway corridor signage that was presented at the PAC June 6th meeting. Ultimately, PAC selected the third option, presented at the July 11, 2019 PAC meeting, to locate public art pieces in various locations along transportation corridors. The three selected include; Carroll Blvd/Carroll Trail (3), Dallas & Teasley median (1), and Eagle & Elm median (1). The procurement process for all three sites are scheduled to being in 2021-2022. Staff presented the placement of sculptures on Carroll, Bonnie Brae and Dallas & Teasley to the Bond Oversight Committee on May 6, 2021. The Bond Oversight Committee recommended the funding be used for the proposed art along city corridors for beautification efforts and to utilize the funding now instead of delaying until the I-35 improvements are completed. Other funding will be sought for I-35 beautification efforts. 2014 Bond Election 1. Street Reconstruction The original intent of this project was for the reconstruction of City streets with an OCI rating of 40 or less and to supplement the 2012 bond program. Beginning with FY 2014-15, the reconstruction program was intended to ramp up to $6 million per fiscal year and continue through the 6-year issuance period of this bond program. Staff believed that 227 additional street segments representing approximately 74.79 lane miles could be completed within the 6 years of the program. To-date, 161 segments have been completed representing approximately 53.27 lane miles. Staff believes that 45 remaining segments will be completed by the fourth quarter of 2022. Seven segments from the 2014 bond are currently being programmed. The seven segments that are currently being programmed as part of other projects include two on Mulberry, which will be folded into phases 3 and 4 of the PEC- 4 Project; two segments on Trinity Road, which will be coordinated with the TxDOT Trinity Bridge Project; and three segments on Westgate Drive, which will be coordinated with the opening of Bronco Way and the new Denton High School. In order to complete the 2014 Street reconstruction projects as well as the connectors between the segments, an additional $7,097,263 was issued in 2018A Certificates of Obligation (COs), which occurred in August 2018, plus $1,680,000 in General Obligation Bonds (GOs) reallocated from the Ruddell Extension Project. Council was presented an update regarding construction cost inflation and budget increases which resulted in the inclusion of $8,900,000 issuance of COs in the FY 2020-2021 budget. Staff has developed a plan to select contractors and construct remaining segments from the 2014 Street Reconstruction Bond by December 2022. 2. Miscellaneous Traffic Signals The original intent of this project was for the installation and/or replacement of traffic signal infrastructure at various locations throughout the City. Below is a summary of remaining signals that need to be installed, including the cost and the project status: Signal Cost Status/ECD Bell/McKinney $310,000 Working with design team to resolve conflict with existing signage on SW corner Bell/Hickory $310,000 Materials Ordered – Construction Scheduled adjusted to Quarter 1 FY 21-22 Locust/McKinney $310,000 Construction started 7/28/21-late October 21’ Elm/McKinney $310,000 Construction started 7/28/21-late October 21’ Below is a list of completed traffic signal installations: Signal Cost Status/ECD Locust/Hickory $350,000 Completed -In Service Since 2018 Locust/Oak $340,000 Completed -In Service Since 2018 Elm/Hickory $250,000 Completed -In Service Since 2018 Elm/Oak $250,000 Completed -In Service Since 2018 Bell/Mingo $380,000 Completed -In Service January 25, 2021 Teasley/Dallas Dr. (Design) $70,000 Completed -In Service Since 2019 3. New Transportation Division Facility This project was previously discussed with the 2014 Bond Oversight Committee on January 30, 2018 and staff was authorized to utilize these project funds ($1,500,000) on reconstructing/remodeling of a City facility located at 651 Mayhill which will house the Transportation Division. The original location of a new Transportation Division Facility was to be located on a property across from the City’s Service Center (Ruddell Street). The cost and delay in the Ruddell Extension project, as well as the availability of another City facility, have necessitated the alternative solution. With the delay of the 651 Mayhill project, efforts are underway to incorporate the proposed Transportation Division functions within the new Development Services Building. Additionally, the project would also include the relocation of the existing Traffic Operation offices to the Service Center building, allowing for the expanded traffic sign and signal division needs. 4. Rail Quiet Zone (McKinney Street to Prairie Street) The original intent of this project was to install specific signalization and infrastructure at the Union Pacific Railroad (UPRR) at-grade crossings located at McKinney Street, Hickory Street, Sycamore Street, and Prairie Street to effectuate a railroad quiet zone. This project was originally scheduled to be completed by July 2019, however that date has been pushed back due to significant staffing changes with UPRR and City staff. Due to requested redesign work from UPRR, it appears that three of the four intersections will be under construction by the end of calendar year 2021 with anticipated completion by the end of Q2 of 2022. 5. Rail Quiet Zone (Union Pacific Railroad North) The original intent of this project was to install specific signalization and infrastructure at the UPRR grade crossings located at Fish Trap Road, Cooper Creek Road, Mockingbird Lane, Nottingham Road, Pertain Street, Willis Street, and Frame Street to effectuate a railroad quiet zone. This project was scheduled to be completed in FY 2018-19, and project completion was dependent on the Ruddell Extension Project. Due to a delay in the Ruddell Extension Project, these quiet zone locations have temporarily been put on hold. Staff recently initiated a new programmatic approach to all City planned projects in the Texas Woman’s University (TWU) area, including the Ruddell Extension Project. On March 23, 2021, the City Council approved a design contract with Bridgefarmer & Associates, Inc. for several projects in the TWU area, including the quiet zones. The anticipated design completion date is Q2 2022. The construction contract for required quiet zone improvements will be advertised following right-of-way acquisition, confirmation of available funds for the current project estimate at completion, and design completion. 6. Bonnie Brae Secondary Arterial from Vintage Blvd. to US-77 (Phases 1 through 6) Phases 1 through 3 of the Bonnie Brae projects consist of the southern portions of Bonnie Brae from I-35E to and including Vintage Boulevard. More specifically as follows: Phase 1 limits are from Roselawn to just north of Vintage. This section provides a new alignment for the roadway and adds two bridges. Phase 2 is the widening of Vintage Boulevard from 2 to 4 lanes from US 377 to I-35W and includes the intersection of Bonnie Brae joining the limits of Phase 1. Phase 3 continues the new alignment of Phase 1 from Roselawn to I-35E. These phases are funded by Regional Toll Revenue funds out of the SH-121 subaccount along with a City of Denton match and are often referred to as Bonnie Brae South we also have up to $5.75M in Denton County funds. These funds cannot be spent north of I-35E on the northern phases of the Bonnie Brae project. Phase 1 is currently scheduled to achieve substantial completion in Q3 2021. Phase 2 is also in the construction phase and is scheduled to be completed in Q3 of calendar year 2021. Phase 3 will be in the bid and award phase by Q4 of calendar year 2021. Phase 4 of the Bonnie Brae project extends from I-35E north to Scripture Street. This phase has been broken into two phases; Phase 4A, which is completed, consists of a Roundabout at the Scripture Street and Bonnie Brae Intersection, and Phase 4B consists of the widening of Bonnie Brae from I- 35E to the Roundabout. The original intent of this project including phases 4A, 4B and 5 was for final design, right-of-way (ROW) acquisition, and construction in the amount of $9,500,000. However, the revised project estimate for phases 4A, 4B, and 5 is now at $28,000,000. In May 2018, City Council approved the reallocation of both $2,479,903 from the FM 1830 and US 377 projects and $1,020,097 from Bonnie Brae Phase 6 into Bonnie Brae Phase 4 to close the funding gap. Phase 4A/Roundabout is complete. Phase 4B is at 90% design and still needs right-of-way (ROW) and utility relocations to accommodate the ultimate widening to a 4-lane divided roadway. In the meantime, the City is evaluating the option of resurfacing and restriping along with working with the North Central Texas Council of Governments (NCTCOG) to provide the additional funding needed for ROW and Construction funding. Phase 5 of the Bonnie Brae project extends from the roundabout to University Drive. Design of this section is at 50% and will also require ROW and utility relocations to accommodate the ultimate widening to a 4-lane divided roadway, as with phase 4B, with the possibility that the existing 4-lane road will be resurfaced and restriped. The project is currently on hold to evaluate the design path, and staff is working with NCTCOG to provide the additional funding needed for ROW and construction past current funding levels from the 2019 Bond. Phase 6 of the Bonnie Brae project extends from University Drive to US-77. The original intent of this project was for design, ROW acquisition, and construction in the amount of $6,100,000 to extend to Windsor Drive. However, the revised project limits have increased the cost to $31,100,000. A new Denton High School will be built north of Windsor Drive, on the west side of Bonnie Brae Street, with an estimated opening date of Q2 of calendar year 2023. Staff intends to coordinate the construction from Windsor to US-77 with the opening of the high school. Design is currently at 100% completion, and we have received environmental clearance from TxDOT. Funding reallocation was approved to move $620,000 from Wheeler Ridge, and $1,786,244 from Bonnie Brae Phase 4 for design into Phase 6. NCTCOG has approved $11,060,800 in federal funding to be applied to the portion of the project extending from Windsor to US-77. Phase 6 is also funded from the 2019 Bond. 7. Miscellaneous Sidewalks The original intent of this project was for the design and construction of various sidewalk projects within the City over the 6-year program period. Staff is finalizing a master sidewalk prioritization work plan in an effort to provide for the systematic design and installation of sidewalk infrastructure responsibly with an emphasis on priority areas. The workplan includes segments currently designed, that are scheduled for construction. Since January of 2021, over 3,000 linear feet of sidewalk has been installed along various streets with another 5,035 linear feet anticipated to be complete by the end of December. The new work plan will be presented to the Committee on Persons with Disabilities, the Traffic Safety Commission and the Mobility Committee for feedback once it is finalized. The sidewalk work plan is currently being reviewed by the recently hired Senior Planner – Bicycle, Pedestrian and ADA Coordinator. Staff is also in the process of closing out existing Traffic funding accounts with the plan of reallocating existing sidewalk funds to ensure more segments are completed annually. 8. Hickory Creek Road - FM 2181 to Riverpass (Hickory Creek Phase 2/West) The original intent of this project was to expand the roadway to a four-lane divided thoroughfare from Teasley to Riverpass. A signal at Montecito and Hickory Creek has been added to the original scope, increasing the revised project cost to $7,500,000. Traffic is providing $350,000 for the signal. In August 2018, City Council approved the reallocation of $2,470,306 from the Ruddell Extension at Mingo Project to the Hickory Creek West Project in order to complete the original scope. This project went to bid in September of 2018. On February 12, 2019, the City Council approved the use of $1,800,000 million in Roadway Impact Fees to allow for the possible reallocation of the same amount in general obligation bonds to the new Hickory Creek (FM 2181/Teasley to Riverpass) project. The project is currently estimated to achieve substantial completion by early calendar year 2022. The project schedule has been impacted by delays and redesigns associated with geotechnical design, franchise utility relocations, value engineering, and development project coordination. 9. Morse Street Expansion to Full Collector Capacity (Loop 288 to Mayhill) The original intent of this project was for design, right-of-way acquisition, and construction in the amount of $2,900,000 to fully convert this roadway to a four-lane divided secondary arterial street, including sidewalks, bike lanes, street lighting and water utility improvements from Loop 288 to Mayhill. This original plan would widen the current three-lane segment between Kimberly and Mayhill to a four-lane divided roadway, matching the existing segment between Kimberly and Loop 288. In May 2018, Council approved the transfer of $250,000 from FM 1830 and US 377 projects and $220,000 in aggregate of other capital improvement projects into the Morse Street Expansion project, raising the Morse Street Expansion funding total to $3,370,000. Subsequently, the scope of the project changed and will now maintain the existing street width along Morse Street between Kimberly Drive and Mayhill Road. The intent is to reduce/reconstruct the existing four-lane segment to a three-lane roadway between Loop 288 and Kimberly Drive. In 2020, $2,600,000 was moved from this project to the Hickory Street from Welch to Carrol project. Staff has considered re-scoping efforts and has included a funding request in the Capital Improvement Plan to provide adequate funds to complete the project. 10. Ruddell Extension to Mingo Road The original intent of this project was for design, ROW acquisition, and construction in the amount of $5,780,000 to align this roadway across the UPRR tracks and provide an improved railroad crossing at Mingo. The revised project cost as originally scoped is $8,602,000. This project was placed on hold for a redesign using $1,629,694 of funding. The remaining funds were reallocated $4,150,306 to: (1) the Hickory Creek Road West project in the amount of $2,470,306 and (2) $1,680,000 on 2014 street reconstruction projects. Staff recently initiated a new programmatic approach to all City planned projects in the Texas Woman’s University (TWU) area, including the Ruddell Extension Project. On March 23, 2021, the City Council approved a design contract with Bridgefarmer & Associates, Inc. for several projects in the TWU area, including 30% design for Ruddell widening from US 380 to Mingo. The anticipated completion date of the 30% design contract is Q4 of calendar year 2021. Staff will include a request to fund the full design and construction of the Ruddell Extension to Mingo in the upcoming capital improvement plan and anticipates potentially bundling several of the TWU area projects in a joint solicitation to have constructed using the Construction Manager at Risk project delivery method. 11. Wheeler Ridge Connection to FM 2181 at Jordan Lane. The original intent of this project was to provide funds in the amount of $620,000 for an alternative point for access into Wheeler Ridge subdivision for residents and emergency service vehicles from Saddle Drive to Jordan Lane and ultimately to FM 2181. This project was scheduled to begin construction in March 2019 and completed in mid-2020. However, after several meetings with the Fire Department this project has been deemed no longer necessary for public safety as there are now alternative routes into the neighborhood. The funding reallocation was approved. COMPLETED 12. Miscellaneous Roadways The original intent of this project was for design and construction of various roadway improvements within the City over the course of the 6-year program period. To date, the City has issued $1,000,000 in GO bonds for this purpose. Staff anticipates the issuance of $500,000 in each of the remaining two years of the bond program and is assessing existing funding needs of active projects for programming. Staff has allocated $600,000 to the Hickory Creek Road project from 2181 to 2499 (East). The cost of this project is estimated at $3,000,000 with additional funding ($2,400,000) coming from TxDOT as part of a Local Project Advance Funding Agreement (LPAFA). 13. Public Art for Street Improvements The 2014 bond program included $30,000 for public art associated with transportation projects. These funds were included in the FY 2019-20 bond issuance. Locations for sculptures have been selected by the PAC to include Carroll Blvd. (3), Dallas & Teasley median (1) and Eagle & Elm median (1). Staff is preparing an RFP for the design and installation of these sculptures with possibly selection by the end of the calendar year. 14. Fire Station #4 Remodel/Rebuild (Sherman Drive) On February 23, 2017, the 2014 Bond Oversight Committee approved the reallocation of $1,100,000 in GO bonds from the Fire Station #3 project. The original cost of the Fire Station #4 project was $5,020,000 and the revised final cost was $6,097,550. Remaining money of $22,540 was moved to the new Fire Station #3 project. This project has been completed and the Grand Opening was held on June 22, 2018. COMPLETED. 15. Fire Station #3 Demolition/Rebuild (McCormick) On February 23, 2017, the 2014 Bond Oversight Committee approved the reallocation of $1,272,000 from this project to bridge the funding gap for Fire Station #4 and the Fire Burn Tower project. At that time, staff informed the Committee that a proposal would be submitted to the City Council to fund any gap in the Fire Station #3 project with Certificates of Obligation (COs). The City Council approved the issuance of COs in May 2018 to fund the remaining $1,685,000. Bonds have been issued and the project is fully funded. Based on the latest engineer’s estimate, which came in extremely high, this project will be bid with alternatives to bring costs down if needed. The project was bid and awarded to O’Haver Contractors for a contract amount of $6,298,000. The Fire Station #3 project began May 2019 and was originally scheduled for completion in December 2020. Staff occupied the building February 12, 2021. Demolition of the old Fire Station #3 has been completed April 2021. COMPLETED. 16. Fire Burn Tower On February 23, 2017, the 2014 Bond Oversight Committee approved the reallocation of $172,000 in GO bonds from the Fire Station #3 project. The original cost of this project was funded by Certificates of Obligation in the amount of $2,721,870 but the revised cost was $2,893,870 which required the reallocation of GOs for completion. The final cost of the project was $2,848,182. Remaining money of $45,687 was moved to the new Fire Station #3 project. COMPLETED. 17. Relocation of Communications Center & Criminal Investigations Bureau The original intent of this project was the remodeling of 6,000 square feet of existing office space and the finish out of 4,500 square feet of unfinished space at the Hickory Street location to accommodate growth in service demands. On February 20, 2019, the Committee approved the reallocation of $1,600,000 for design and other preliminary costs related to the Police Station Renovation project included in the Proposed 2019 Bond Election. The remaining funding of $10,368 was moved to the Police Facilities Project (Design). REALLOCATED 18. Police Firing Range with Ten Foot Berm Addition The original intent of this project was for safety and security enhancements, including improvements to the entrance gate, landscaping, security, drainage, parking, berm height, and the construction of a permanent range house. The original cost of the project was $485,000 but this has been revised to $1,105,000. This additional $620,000 was sold in the 2018A Certificates of Obligation (COs) issuance which occurred in August 2018. The project is temporarily on hold for review by the new Chief of Police, Chief Dixon. Staff is requesting to reallocate $299,061 of GOs to the proposed police facilities. On February 20, 2019, the Committee approved the reallocation of the remaining GOs to the proposed police facilities project. REALLOCATED. 19. Police Facilities Project (Design) This project is in the design development phase. The City Hall East Police Department remodel and new sub-station was awarded through the RFQ process for $3,085,830 to Brandsetter Carroll Architects. COMPLETED 20. Public Art for Public Safety The 2014 bond program included $325,000 for public art related to public safety projects. These bonds have been issued, and to date, $253,401 have been spent on the Bell Tower project at the Central Fire Station and $9,300 has been spent for engineering services related to the mounting of two brick-art panels at the Police Station and $28,330.61 has been encumbered. The current remaining balance for Public Safety art is $62,299. City Council approved the contract for the sculpture on August 24, 2021. 21. Eagle Drive Drainage Improvements Phase 2 The original intent of this project was for the drainage box and channel improvements from east of Elm Street to Eagle drive in the amount of $2,097,000. Construction began in August 2018 and is now complete. The revised project cost came to $2,721,627 and project construction was completed in October 2019. COMPLETED 22. PEC-4 Drainage Improvements Phase 2 – West of Locust to Prairie The original intent of this project was for the design and construction of drainage improvements from East of Locust Street to Prairie Street along the alignment of PEC-4. This project began construction in July 2019 and is currently on schedule with an estimated completion by the end of Q3 of calendar year 2021. 23. Downtown Drainage Projects These projects are comprised of the (a) Hickory Street Drainage & Trunk Line System ($600,000), (b) South Bell Drainage System ($806,000), and (c)(3) Oak Street Drainage projects (does not include GO funding). These projects have been broken up into two phases. Phase 1 is the Oak Street Drainage and half of Hickory Street trunk line from McKinney to Hickory (this phase of the project is also referred to as Downtown Storm Sewer Phase 1). Phase 2 is the South Bell Drainage and second half of Hickory Street trunk line from Hickory to Sycamore (this phase of the project is also referred to as Downtown Storm Sewer Phase 2). The total revised project cost for both phases is $3,135,000. Phase 1 is currently funded. Staff is seeking additional funding for Phase 2. Construction for Phase 1 began in December 20201 and is on schedule for completion in Q4 of calendar year 2021. 24. Magnolia Street Drainage Phase 2 (Hinkle Project) The original intent of this project was for the construction of a separate storm drain system to capture, contain, and convey the runoff from the upper portion of the watershed to the outfall at Pecan Creek, south of Good Samaritan Village. This project would further alleviate flooding in the area and enable the reconstruction of Hinkle Drive. The original cost for this project was $2,557,000. The construction contract for this project was awarded on February 5, 2019, and construction was completed by May 2020. A scope change occurred that entailed the addition of a roundabout at Hinkle and Mimosa along with additional curb installation and rock excavation that increased costs to $7,550,000. In May of 2018, City Council approved the use of drainage channel rehab funds in the amount of $1,737,836 to aid in bridging the funding gap. This project was substantially completed in 2020 and reported as complete at the November 5, 2020 Bond Oversight Committee meeting. Retainage has been released for this project, and as of Q3 2021, this project is completed. The Streets Division of the Public Works Department is coordinating an adjacent project to complete a bicycle path and visibility enhancements to improve safety of the roundabout. COMPLETED 25. Playground Replacements The original intent of this project was to fund the replacement of seven play structures at Milam, Nette Shultz, Carl Young, Fred Moore, Denia, McKenna, and Evers Parks to meet current Consumer Product Safety Commission playground standards. Parks and Recreation received approval to transfer a portion of the balance of funding, approximately $77,000, allocated for McKenna Park playground to be redirected to Joe Skiles Park Playground. McKenna Park has over $1,200,000 in 915/916 funding that can only be used in an approximate 1- mile radius of various developments around the park. This funding was used for the purchase and installation of the McKenna Park playground instead of the bond funding. • Evers Park Playground- Completed • Milam Park Playground- Completed • Fred Moore Park Playground- Completed • Denia Park Playground- Completed • Carl Young Park Playground- Completed • Nette Shultz Park Playground- Completed • McKenna Park Playground- Completed Additional playground completed • Joe Skiles Park Playground Completed After completion of the listed playgrounds, it is anticipated that $177,955 would remain for reallocation to another project. Staff requested $150,000 of this available funding to be moved to the South Lakes Park Improvement project to cover the shortfall expected for the new tennis courts and lighting. Staff requested the remaining $27,955 to be moved to the new North Lakes Tennis Center project and was approved by the Bond Oversight Committee on February 4, 2021. COMPLETED. 26. Park Improvements The original intent of this project was to improve several parks, including the addition of two lighted tennis courts at South Lakes Park and improvements at Lake Forest Park. Funding was obtained in May 2018 for a total of $300,000. The pavilion and basketball court projects at Lake Forest and Milam Parks were completed through an endowment from a private foundation therefore the $150,000 identified for Lake Forest improvements can be used elsewhere. The South Lakes Park tennis court and lighting project was originally funded for $150,000. Estimated costs of construction as of October 2018 were $250,000. Staff received approval to reallocate the Lake Forest pavilion funding of $150,000 to eliminate the funding gap to build the two new lighted tennis courts and add lighting to the existing courts as a bid alternate. This will expand playability of the courts as well as provide cooler times for patrons to utilize the facility. A public meeting for the park was held in July 2019 to gather input on various park projects and for the master plan. Design for South Lakes Park tennis courts was thought to be complete, but additional engineering was required. Adams Engineering has been hired to complete the design and provide oversight during construction. Staff received approval to use of $150,000 remaining in the playground project to cover this funding gap and was approved by the BOC. Lowest bid received was $410,770 for the two new courts with lights. Per the Procurement Timeline Tool, below are the following dates for the project to proceed. 1. Start bid solicitation May 5, 2021 2. Bid Opening August 10, 2021 3. Council Approval September, 2021 4. Construction NTP 30 days after Council approval 5. Substantial Completion Summer 2022 6. Final Completion Summer 2022 27. Property Acquisition (for Parks & Libraries) The original intent of this project was to fund the purchase of new parkland in the City. PARD staff has identified potential parcels of interest. In June 2020, the funding of $1,005,000 was again available to be utilized for purchase of land. Staff presented land option to City Council in August 2020 and February 2, 2021. A total of (3-4) parcels have been identified as potential locations for a park and library. One location was determined to be unavailable for acquisition and the other three are currently being negotiated for acquisition by Real Estate. 28. Southwest Park Master Plan & Design The original intent of this project was for master planning and design services necessary for the development of the park, including survey, platting, and environmental assessments. This information would then become part of the master plan for the development of the park which eventually could include a recreation center, athletic facilities, aquatic components, and trails. A survey of the land was completed in the summer of 2019 in preparation for the project. Staff has completed a Request for Qualifications (RFQ) and conducted interviews in January 2020 to hire a consultant. COVID-19 caused a delay in this project. The contract was approved by City Council in June 2020 and a kick-off meeting was conducted on July 14, 2020. In addition, a citizen focus group was created, and several public meetings have been held to gather feedback and information from the community. Parks and Recreation received approval from the committee to use $175,000 to assist in hiring consultants to complete the City-wide PARD master plan. Internal staff that was working on the project left the organization in February, then COVID-19 caused a pause in the process. Due to the lack of staff and workload, Parks and Recreation hired Halff Associates to help the department complete the plan. The Parks, Recreation and Trails System Master Plan will be completed at the end of the calendar year. It is anticipated this project will have a remaining balance of $856,161 after completion. Staff requested moving this balance to the North Lakes Tennis Center project to bridge the anticipated funding gap and was approved by the Bond Oversight Committee on February 4, 2021. A concept plan for Southwest Park has been completed and proposed to the focus group and Parks, Recreation and Beautification Board for feedback. Staff is planning on presenting to City Council for feedback on October 4, 2021. Once this feedback is attained, staff will make any needed adjustments and process this through for final review and approval with the focus group, Parks, Recreation and Beautification Board and City Council. 29. Sprayground The original intent of this project was to fund the construction of a small/medium splash park. The park would contain spray jets and water features such as water cannons and dumping buckets. The original cost for this project was $200,000 but was revised to $395,515. The funding gap was bridged with Park Development funds in the amount of $195,515. The project has been completed and was dedicated on May 12, 2018. The final cost of the project was $381,488, leaving $14,026 in available funding, of which $13,629 was bond funded and $397 was from Park Development funds. Staff received approval to reallocate the remaining bond funds of $13,629 toward the purchase of restrooms at Carl Young Park, which was completed this Summer. The Carl Young Park restroom facility was completed under budget and the reallocation was not needed for the project. In November 2020, the Bond Oversight Committee approved reallocation of the remaining $13,629 to the North Lakes Tennis Center project. COMPLETED 30. Trail System Expansion & Addition The original intent of this project was to fund the expansion of the off-road pedestrian trail network, allowing citizens access to parks and recreation centers and providing safe routes for work, school and shopping centers. The advanced trail project is the Northwest Trail Extension off Highway 77 and Nacosia which connects the Evers Trail to North Lakes Park. This project was completed in 2017. In the spring of 2021, TXDOT sent the city a communication notifying the city that a balance was identified of $42,940. Staff is currently identifying funding to pay this balance. COMPLETED 31. Tennis Center Remodel & Expansion The original intent of this project was to fund the relocation and expansion of the Goldfield Tennis Center to include 12 tennis courts, ADA accessibility improvements, and a new pro shop. The revised budget for this project is $3,787,829 which includes $3,445,000 from the 2014 bond program, $250,000 from the 2005 bond program, and $14,197 in other (non-bond) funding. Additionally, in November 2020 the Bond Oversight Committee approved reallocation of $13,629 from the completed Sprayground project and $65,000 from the completed Vela Athletic Complex project. Staff submitted a USTA grant totaling $100,000 to assist in the construction. The City of Denton was awarded $30,000 from USTA and another $10,000 from USTA Texas. These grant funds are not currently listed as part of the project budget but will be added once received. The planning and design process began in June 2018. Parks and Recreation staff created a concept design and estimated costs. The Parks, Recreation and Beautification Board and City Council were briefed in August 2018 on the draft design. A public meeting was held on August 9, 2018 along with numerous focus group meetings that included, USTA, UNT, Denton Tennis Association, local tennis professionals, and pickle ball participants. The Parks, Recreation and Beautification Board recommended the design to City Council on February 4, 2019. City Council approved the concept design and approved a design contract on May 7, 2019. Construction on the pro shop was projected to be completed in January 2021 but was substantially completed in October 2020. Staff requested remaining funds from the Southwest Park Master Plan project of $856,161 and a portion of the remaining funds from the Playground project, $27,955, to be allocated to the North Lakes Tennis Center project and was approved by the Bond Oversight Committee on February 4, 2021. Per the Procurement Timeline Tool, below are the following dates for the project to proceed. 1. Start bid solicitation July 30, 2021 2. Bid Opening August 31 , 2021 3. Council Approval October, 2021 4. Construction NTP 30 days after Council approval 5. Substantial Completion Winter 2022 6. Final Completion Winter 2022 32. Water Works Park Additions (Wave Pool/Concession Stand) The original intent of this project was for the construction of a new wave pool, permanent concession facilities, and additional shade areas. The original cost for this project was $2,443,000 but this was revised to $2,800,094. The funding gap for this project was primarily funded with $300,000 from the Parks Gas Well fund. The Wave Pool project opened in the summer of 2017. The concession stand was completed and open for operations along with the entire Water Works Park in May 2018. An additional $35,000 was added to the project for a wave pool study. The warranty has been extended by the contractor for two years and some additional work was completed in early 2020. Costs have been finalized at $2,796,476. COMPLETED 33. Vela Soccer Complex Phase II Construction The original intent of this project was to complete Phase II construction of the Vela Athletic Complex at North Lakes Park, including a permanent concession area; year-round restroom facilities; a large pavilion to accommodate tournaments; connecting sidewalks; and a playground structure. The original project cost estimate was $1,333,000. City Council approved the complete construction of the project in early May 2018 for a total project cost of $6,363,532. Total project costs include site development expenditures that were incurred prior to construction. Construction began May 21, 2018 and was completed in May 2019. An official dedication occurred on May 26, 2019. A grand opening was held on August 31, 2019. While the overall project is completed, some signage is being planned in cooperation with the Vela family and LULAC. Two plaques will be placed on an interior wall and an arch at the entrance was recently installed to welcome participants to G Roland Vela Athletic Complex. Parks and Recreation has also been working with the Public Art Committee on the procurement of a sculpture within the athletic complex. Initially, $35,000 was allocated from HOT and Bond funds. Additional funding was required for the desired theme and sculpture. Staff received approval from the Bond Oversight Committee meeting to use $65,000 from the Vela construction project towards this piece of art. Additionally, a $1,000 donation was received from the Denton Parks Foundation to add to the project budget. City Council approved the concept for a total of $101,000, including $95,000 for the project and $6,000 in contingency. It is anticipated that the sculpture will be installed in the Summer of 2021. After completion of the signage, archway, and sculpture it is estimated the balance of bond funding remaining in this project will be approximately $65,000. In November 2020 the Bond Oversight Committee approved the reallocation of these funds to the North Lakes Tennis Center project. Sculpture is under construction and will be installed in late Summer 2021. COMPLETED 34. Emergency Action Plan – Lake Forest Dam The outcome of the engineering plan will cover construction documents, cost estimates of construction, financial considerations, project scheduling, 404 permitting (permit through EPA for discharge of dredged material), water rights through TCEQ, dam breach mapping, and an Emergency Action Plan (EAP), dam rehabilitation design, dredging plan, operations and maintenance plan, and construction administration through construction phase. This project will be funded with $250,639 in General Obligation (GO) Bonds reallocated from the Clear Creek Heritage Center project and $95,361 in aggregate savings from other parks capital improvement projects in the amount of $448,902. Assessments and construction drawings have been completed and funding to the total of $3,000,000 from the FY19-20 budget has been allocated for construction. The project was bid in November 2020. Bids came back higher than expected and staff identified an additional $300,327 to bridge the funding gap. Council approved the project and construction began in April 2021. The contractor is currently moving sediment from the pond. The project will be delayed due to the amount of rain received in the spring. 35. Public Art for Parks The 2014 bond program included $180,000 for public art related to public parks projects. The City has issued $180,000 in bonds for these projects, and to date, $100,000 has been spent on two sculpture projects at City Hall (Morales) and the Civic Center (Surls). The Public Art Committee (PAC) voted March 7, 2019 to proceed with a $35,000 public art project at North Lakes Dog Park comprised of $20,000 in bond funds and $15,000 from the committee’s 2019 Hotel Occupancy Tax budget. Similarly, the committee voted April 4th, 2019 to proceed with a $35,000 public art project at the Vela Soccer fields, comprised of $20,000 in bond funds and $15,000 from the committee’s 2019 Hotel Occupancy Tax budget. Additional funding of $65,000 was allocated from the Vela Athletic Complex construction account to assist with the procurement of the sculpture. The committee determined a site for placing public art at the North Lakes Tennis Center but delayed assigning a budget and funding source(s) until the tennis court design is completed. The PAC has selected the artist for Vela, received City Council approval, and this project is now in fabrication. The original proposed art for the North Lakes Dog Park project was rejected by the subcommittee. Staff rebid the project, bids were received, and a concept was approved by the PAC on April 16, 2021. The concept and contract were be presented and approved by City Council in May 2021. Planned dedications of sculptures are as follows:  “Fetch”, North Lakes Dog Park – Dedication September 10, 2021  “Vela’s Trophy”, Vela Athletic Complex - Dedication September 18, 2021 2019 Bond Election: 1. Bonnie Brae (Phases V, VI, VII) The 2019 Bond Program provides funding for Phases V, VI, and VII to widen approximately three miles of Bonnie Brae Street from Scripture Street to Loop 288 and build a continuous four lane divided roadway along this route. Phase VI is currently at 100% design with right-of-way acquisition underway and construction projected to start later this year. Staff is coordinating closely with the Denton Independent School District with a goal to have Phase VI substantially complete in Q2 of 2023, with staff aiming to coordinate lane openings with the opening of the new Denton High School. Phase V and VII both need to be designed and additional project funding needs to be identified for completion, with Phase VII to be designed and constructed by the Texas Department of Transportation (TxDOT). 2. Hickory Creek (Phase 3) The 2019 Bond Program provides funding for the widening of approximately one mile of Hickory Creek Road from Riverpass Drive to FM 1830 (Country Club Road) to a four-lane divided roadway including a bridge designed to accommodate expansion at some time in the future as demand increases. This project is often referred to as Hickory Creek Phase 3. This project is currently at 90% design and right of way acquisition is actively underway. Project construction is anticipated to start by Q2 of calendar year 2022 and is projected to be complete by Q2 of 2024. 3. Street Rehabilitation Program The 2019 Bond Program provides funding for the design and reconstruction of aging street infrastructure throughout the City. In addition to the street itself, curb and gutters, sidewalks, traffic signals, turn lanes, medians, and other components may be included in a street rehabilitation project. Programming for these streets and the associated impacted infrastructure is ongoing. Construction solicitations for the first two bid packages of the 2019 Street Rehabilitation Bond were advertised on January 11, 2021, a contractor has since been selected and construction for the first bid package of the 2019 Street Rehabilitation Bond initiated the week of July 14, 2021, with scheduled completion in Q4 of 2021. Construction for the second bid package of the 2019 Street Rehabilitation Bond initiated on July 19, 2021, with scheduled completion in early Q1 of 2022. On June 22, 2021, the City Council approved a design amendment with Freese and Nichols, Inc. (FNI) to complete the design of the first phase of the Southeast Denton Street Reconstruction Project, which will reconstruct 22 street segments approved as part of the 2019 Street Reconstruction Bond. Staff anticipates the first phase of the Southeast Denton Street Reconstruction Project will begin construction in Q2 of 2022. A second bid package utilizing the Construction Manager at Risk methodology will complete the remaining 51 street segments in the Southeast Denton neighborhood. Staff anticipates that the new Construction Manager and design firm will be selected for the second phase of the Southeast Denton Street Reconstruction Project by November 2021. The design amendment approved on June 22 with FNI also authorized eighteen months of Program Management services for the 2019 Street Reconstruction Bond. Program Management services provided by FNI include development of a comprehensive sequencing plan for all 2019 Street Reconstruction Bond segments, the development of dashboards and other key reporting features that can be shared internally and with the public regarding the status of project construction, preparation of cash flow models and individual project estimates, project execution process tracking, and providing general project implementation oversight. Staff and FNI currently anticipates completing all street reconstruction segments included in the 2019 Bond by the close of calendar year 2026. 4. Sidewalks Sidewalk infrastructure will be installed according to the City's sidewalk prioritization workplan. The plan seeks to close existing sidewalk gaps and install new sidewalks within one-quarter mile of schools, universities, parks/greenbelts, and public transportation within the City of Denton. A single project manager has been assigned for the full implementation of the sidewalk prioritization workplan, with focus on ensuring the timely completion of design and construction of segments utilizing the $12 million in sidewalk funding included in the 2019 bond and will help coordinate sidewalk projects with roadway reconstruction and other infrastructure investments. In January 2021, staff received approval from the City Council for a $2.5 million application to the Denton County Transportation Authority (DCTA) for funding through the Transportation Reinvestment Program. DCTA confirmed the application was successful in June 2021 and the funding will be used to complete the Safe Routes to School sidewalk projects at Ginnings, Alexander, Nette Schultz, and Pecan Creek Elementary Schools and augment funding for segments currently listed on the sidewalk work plan. The new sidewalk work plan will be presented to the Committee on Persons with Disabilities, the Traffic Safety Commission and the Mobility Committee for by the end of calendar year 2021. The draft sidewalk work plan has also been used to inform the capital improvement plan for the upcoming fiscal year. 5. Street Lighting The 2019 Bond Program provides funding for the design and construction of streetlights along US- 380 (University Drive) between I-35 and Mayhill Road and where street lights were not added by TxDOT during construction of its US-380 roadway project. This area carries a significant amount of pedestrian, and vehicular traffic, and a portion of this segment is adjacent to Texas Woman’s University. Staff recently initiated this project with DME and anticipates selecting a design firm once the first bond issuance for this project becomes available in FY 2023-2024. 6. Ryan Road The 2019 Bond Program will provide funding for the widening of approximately two miles of Ryan Road, from Teasley Lane to Country Club Road, from a two-lane road to a three-lane road. On February 23, 2021, the City Council approved a 30% design contract with Kimley Horn for this project. The 30% design should be completed in Q3 of 2021. In order to ensure east/west access to FM 1830 as Hickory Creek Road Phase 3 is under construction (extents for Hickory Creek Road Phase 3 are from Riverpass Drive to FM 1830), final design and construction of the project will be coordinated so that construction will not begin on Ryan Road until construction of Hickory Creek Road Phase 3 is completed. Staff currently projects a Q2 2024 completion date for Hickory Creek Road Phase 3. Staff anticipates Ryan Road will take approximately one year to construct, but construction will need to be coordinated to ensure access to Ryan Elementary. Staff tentatively projects a Q3 2025 completion date for Ryan Road to account for project coordination with school traffic. 7. Police Renovation Project The 2019 Bond Program provides funding for the renovation of the existing Police Headquarters at City Hall East (601 E. Hickory St.). The City Hall East building was originally constructed in 1947 and expanded in 1965. The building was donated to the City of Denton in 1990 and was renovated in 1992-1994 for city operations. In 2013, unfinished space was converted to create the Denton Public Safety Training Facility. The Construction Manager at Risk (CMAR) firm, Byrne Construction, started pre-construction services earlier this year, after being awarded through a competitive Request for Qualifications & Request for Proposal process. The CMAR has solicit subcontractor bids from the 100% Construction Documents, which has been received with the full participation and oversight by City and Peak Program Value (PPV). After a bid analysis and award process run by the CMAR, and vetted by the City staff and PPV, the CMAR will prepare a Guaranteed Maximum Price (GMP) Amendment for City Council consideration. Council approved the GMP on December 1, 2020. The project is starting construction in Q1 of 2021, and all three facilities will be operational by Q2 of 2022. The current budget consists of the issued GO/CO in the amount of $47M. Approximately $40M has been spent or encumbered to date. 8. Police Substation Range The 2019 Bond Program provides funding for the construction of a new Police Substation adjacent to the existing Fire Station 7 on Vintage Boulevard. The substation is intended to house patrol, neighborhood services, traffic enforcement, criminal investigation, and other operations and staff and administrative support. See section 7 for schedule and budget update. 9. Police Indoor Firing Range The 2019 Bond Program provides funding for the construction of a new Police Indoor Firing Range adjacent to existing Fire Station 7 and the proposed Police Substation on Vintage Boulevard. See section 7 for schedule and budget update. Exhibits 1. Agenda Information Sheet 2. Summary of GO Funded Projects 3. Parks Bond Program Presentation 4. Capital Projects Bond Program Presentation 5. Facilities Bond Program Presentation 6. Bond Issuance Timeline Prepared By: Respectfully Submitted: Sunita Gautam Cassey Ogden Financial Analyst Director of Finance