MEMORANDUM
DATE: May 30, 2025
TO: The Honorable Mayor Hudspeth and Council Members
FROM: Sara Hensley, City Manager
SUBJECT: Friday Staff Report
Upcoming Meetings
A.Parks, Recreation and Beautification Board on Monday, June 2, 2025, at 6:00 p.m. in theCivic Center Community Room.
B.Work Session of the City Council on Tuesday, June 3, 2025, at 3:00 p.m. in the CityCouncil Work Session Room followed by a Regular Meeting at 6:30 p.m. in the CouncilChambers.
C.CANCELLED - Agenda Committee on Thursday, June 5, 2025, at 8:00 a.m. in the CityCouncil Work Session Room.
D.CANCELLED - Downtown Economic Development Committee on Thursday, June 5,2025, at 8:30 a.m. at the Development Service Center.
Please check the City of Denton website for final meeting days and times as information is subject to change after the Friday Report is published. Public Meetings & Agendas | Denton, TX (civicplus.com)
General Information & Status Updates
A.Monthly Financial Reports – The Monthly Financial Report provides a year-to-date
comprehensive overview of the City of Denton's financial performance, including keyrevenue and expenditure highlights, as well as budget variances. The Monthly FinancialReport can be accessed here. Staff contact: Vis Bouaphanthavong, Finance
B.Monthly Mobility Report - Innovative Transportation Solutions (ITS) provides a monthly
report that includes an overview of Texas Department of Transportation (TxDOT) regionalprojects. See the attached ITS Monthly Mobility Report for review. Staff contact: SethGarcia, Capital Projects
C.DTV Video Highlights for May - DTV released several videos this month. The following
are highlighted videos that the Council is encouraged to share:
•Summer Reading Challenge 2025 YouTubeBring color to your world this summer with the Summer Reading Challenge!
•Denton Animal Shelter Adopts New Tech YouTube
The implementation of new staff-led technology at the Denton Animal Shelter issetting a new standard for animal care.
•Water Works Park Opens This Weekend! YouTube
Grab your swimsuits and sunscreen; it's time for Water Works Park to open!
•Story Time Meets History in Denton YouTubeAs part of Denton's Historic Preservation Month, the Denton Public Library hosted a special story time. All videos air on DTV, are shared via social media channels, and are available on the
City’s YouTube channel. Staff contact: Billy Matthews, Marketing and Communications
D.Mayor’s Pet Spotlight – “Rowdy” Roma is ready for a new owner! This year-old,Pit/Labrador mix was brought into the shelter as a stray on February 28. With some much-needed TLC and office time,
the staff helped her decompress. Now, Roma walks on a
leash and does well in the office environment.
She needs someone patient who can help train her to manage this behavior. Roma is very dog-friendly and is the star of
our playgroups with other dogs at the shelter.
Staff continue to provide her with toys, runs, playgroups, and office time, but the noise and stress of the shelter are taking
a toll on her. Staff hope that being featured as the Mayor's
Pet Spotlight will help Roma find the loving home she deserves.
Please contact Denton Animal Services by phone at (940) 349-7594, or via email at
Animal.Services@cityofdenton.com. Staff contact: Bailey Coleson, Animal Services
2
Responses to Council Member Requests for Information
A.Hobson Lane Closure Update – On May 18, Council Member Holland requested
information on the closure of Hobson Lane. A developer is constructing a right-hand turnlane and other public infrastructure to serve the development. Staff met with the developeron May 27 to discuss expediting work on Hobson Lane to minimize roadway closures. OnJune 2, the developer plans to close the roadway to install electrical conduit crossingHobson Lane and complete excavation for subgrade placement. The roadway is expected
to be closed for five to seven days. Staff will work with the developer to open the roadwaywhenever possible. Other short-duration closures will be implemented over a three to four-week period until all public work is complete. Staff contact: Seth Garcia, Capital Projects
B.Sidewalk Repair – On May 20, Council Member Holland shared an inquiry from a resident
regarding sidewalk repair on Wellington Oaks. Staff investigated the site and has slatedthis on a list of repairs to occur by the end of the year. Staff contact: Jeremy Wilks, PublicWorks – Streets
Attachments
A.Monthly Mobility Report ……………………………………………………………........5
Information from the City Manager
From time to time, I would like to share with the City Council local government-related resources
that I find insightful, interesting, or timely. These may be studies, periodicals, reports, or web resources. My intent is to make the Council aware of broad perspectives and discussions and not to suggest any policy or service change. – Sara
Agreements to provide emergency services outside the local city jurisdiction strain resources. Our
neighbors to the east are also reevaluating their relationship with the rural community they serve. There are a few articles that address the issues many rural communities and cities now face.
Citizens in Collin County are looking into options similar to those that we have implemented here with the Emergency Services District to help improve the economic impact that local cities face when serving unincorporated areas. Please view the article here.
Budget constraints are prevalent in the local government sector. Georgetown is exploring various ways to adjust and mitigate the budget deficit. Please view the article here to learn more about similar strategies and tactics that they are using to help reduce the deficit.
3
Upcoming Community Events and Public Meetings
Please visit the City of Denton website for upcoming community events and details.
Information
A.Council Requests for Information .......................................................................................22
B.Public Meetings Calendar ...................................................................................................24
C.Future Work Session Items .................................................................................................28 D.Street Closure Report ..........................................................................................................29
4
City of Denton Transportation Update Prepared by:
May 2025 1
City of Denton Transportation/Mobility
Project Status Report
Prepared by ITS
May 2025
PROJECTS
•Project Summary ............................................ page 2
•I-35 North ....................................................... page 3
•I-35/35E/35W Merge...................................... page 5
•I-35E/Mayhill ................................................. page 8
•I-35W Frontage Roads Middle ....................... page 9
•Loop 288 West Frontage Roads ................... page 10
•Loop 288 East-US 380 Connector ................ page 11
•Bonnie Brae Segment 7 ................................ page 12
•FM 1515 ....................................................... page 13
•FM 1173 ....................................................... page 14
•Outer Loop.................................................... page 15
•Glossary of Acronyms .................................. page 16
•TxDOT Funding Categories ......................... page 17
•Denton City Limits ....................................... page 18
5
City of Denton Transportation Update Prepared by:
May 2025 2
PROJECT SUMMARY
PROJECT LET DATE CONTRACTOR/
ENGINEER
CONSTRUCTION
COST
I-35 North Various Stantec $897,796,423
I-35/35E/35W Merge 04-2024 Sema Construction $588,780,841
I-35E/Mayhill 06-2025 LTRA $139,130,349
I-35W Frontage Roads Middle 09-2028 WSP $446,891,327
Loop 288 West Frontage Roads 09-2028 CP&Y $227,423,354
Loop 288 East-US 380 Connector * Westwood $1,262,000,000
Bonnie Brae Segment 7 * Westwood *
FM 1515 * LTRA $69,484,709
FM 1173 * Halff $125,852,145
Outer Loop * LJA $1,547,212,128
TOTAL $5,304,571,276
6
City of Denton Transportation Update Prepared by:
May 2025 3
Current Activity:
•PS&E: Work on the 100% PS&E plan set for the -074 CSJ is underway with updates to 2024TxDOT Specifications. Additionally, TxDOT plans to split -074 CSJ into three separate CSJs forletting. Update to project schedule to accommodate for project split is forthcoming.
I-35 North
CSJ: 0195-02-074; 0195-02-076; 0195-02-081; 0195-
01-116; 0195-02-084 Schematic Approval: January 31, 2019
Limits: From US 77 to FM 3002 (Cooke County line) Environmental Approval: October 7, 2019 Length: 12.4 miles
Description:
Reconstruct and widen 4- to 6-lane rural
freeway with ramp modifications and
reconstruct 4- to 4/6-lane frontage roads
ROW Acquisition Complete: July 2023
Est. Construction Cost:
$897,796,423 -074: $495,359,007
-081: $175,274,676-116: $110,895,970
-084: $116,266,771
Utility Relocations Complete:
-074: January 2026
-081: June 2025
-116: October 2025
-084: October 2025
Funding:
$801,507,230
CAT 4: $220,966,122
CAT 11: $2,574,631
CAT 12: $577,966,477
100% Plans:
-074: *
-081: May 2025
-116: June 2025
-084: June 2025
Firm: Stantec Ready to Let Date:
-074: January 2026
-081: June 2025
-116: October 2025
-084: October 2025
TxDOT PM: Dawit Abraham Let Date:
-074: July 2026
-081: August 2025
-116: December 2029
-084: December 2029
7
City of Denton Transportation Update Prepared by:
May 2025 4
•Work on the 100% PS&E plan set for the -081 CSJ is underway with updates to 2024 TxDOT
Specifications; TxDOT is revising scope to ensure that the project scope fits within the availablefunds.
•Work on the 100% PS&E plan set for -084 CSJ is underway with updates to the 2024 TxDOT
Specifications; some scope being shifted to -081 CSJ.
•Utilities: Status of utilities in conflict is listed below by CSJ/Segment.IH-35 from US 77 to South of FM 455; CSJ: 0195-02-074
•Utilities that are clear of construction: Atmos Distribution, City of Denton, Frontier,Nortex, OneOK, and Sanger Electric.
•Utilities that are currently relocating: Bolivar WSC, Brazos Electric, CoServ Electric,CenturyLink/Brightspeed, and UTRWD.
•Utilities that are pending relocations: Altice, MCI/Verizon, and Zayo.
•Utilities that are critical path: NoneIH-35 from North of FM 455 to View Road; CSJ: 0195-02-081
o Utilities that are clear of construction: AT&T, Bolivar WSC, Brightspeed/CenturyLink,Lumen/Level 3, Nortex, Sanger Electric and Sanger Water/Wastewater.o Utilities that are currently relocating: MCI/Verizon and Zayo.
o Utilities that are critical path: MCI/Verizon.IH-35 from View Road to Cooke County Line (FM 3002); CSJ: 0195-02-084
•Utilities that are clear of construction: AT&T, Bolivar WSC, CoServ Electric,Lumen/Level 3, Nortex, and Sanger Electric.
•Utilities that are currently relocating: None.
•Utilities that are pending relocations: MCI/Verizon, Oncor, and Zayo.
•Utilities that are critical path: None.
8
City of Denton Transportation Update Prepared by:
May 2025 5
Current Activity:
•Construction: The project let for construction on April 4, 2024. The project was awarded toSema Construction with a low bid of $588,780,840.70, at 18% above engineer’s estimate.There are 1,356 working days and 56 months of barricades. See attached TxDOT constructionreport.
•Utilities: The status of utilities in conflict is listed below.
o Utilities that are clear of construction: AT&T, Atmos Distribution, Atmos Transmission, BrazosValley Electric, Charter/Spectrum, City of Denton Water/Wastewater, CoServ Electric, DMEDistribution, DME Transmission, Fiberlight, Frontier, Lumen, MCI/Verizon, UPN, and Zayo.
o Utilities that are currently relocating: City of Denton sewer.o Utilities that are pending relocation: None.o Utilities that are critical path: Atmos and UPN have conflicts with installation.
I-35/35E/35W Merge
CSJ:
0195-03-099 (N Texas Blvd to I-35E/W)
0195-03-090 (I-35E/W to US 380)
0195-03-087 (US 380 to US 77)
Schematic Approval: -090: August 2011
-087: January 31, 2019
Limits: From North Texas Blvd to US 77 north of
Denton Environmental Approval: -090: June 2017
-087: October 7, 2019
Length: 5.073 miles ROW Acquisition Completed: May 2022
Description:
Reconstruct interchange and existing
frontage roads; reconstruct and widen to 6/8-
lane rural freeway with ramp modifications
Utility Relocations Complete: May 2025
Est. Construction Cost: $588,780,841 City of Denton Utility Relocations Completed: December 2024
Funding:
$588,780,841
CAT 2: $65,978,054
CAT 3: $1,452,495
CAT 4: $75,042,004
CAT 11: $106,973,305
CAT 12 (Strategic Priority): $219,334,983
CAT 12 (Texas Clear Lanes): $120,000,000
100% Plans: January 2024
Firm & Key Contact: AECOM (-090); Stantec (-087) Let Date: April 4, 2024
TxDOT PM: John Rich Construction Completion: November 2029
9
City of Denton Transportation Update Prepared by:
May 2025 6
TxDOT Monthly Project Report
Date of report: May 7, 2025
Report prepared by: Jonathan Rich
Project: 0195-03-087, ETC
Control: 0195-03-087, ETCA Highway: IH 35 Limits: IH35E at North Texas Blvd to North of US 77 on IH35 Contractor: Sema
TxDOT Project Manager: Jonathan Rich Phone: (945) 290-0731 Contractor’s Project Manager: Shea Hurley Phone: (720) 215-8056
Date Work Began: January 13, 2025 Anticipated Completion Date: November 2029
Current Activities:
Current activities: Finish earthwork and start placing asphalt and concrete at I-35W future off-ramp for FM 1515. Continue retaining wall at I-35W future off-ramp for FM 1515. Continue temporary shoring wall for detour along northbound frontage
road from Bonnie Brae to Oak Street and southbound frontage road from Oak Street to Airport Road. Continue placing temporary detour at eight locations including southbound main lanes, northbound frontage road, and southbound frontage road. Small traffic switches will be done in the next coming weeks. Finish placing drainage along southbound frontage road from Bonnie Brae to North Texas. Continue placing drainage from Scripture to US 380 and US 380 to Loop 288. Start permanent drainage from US 380 to Airport Road. Finish partial culverts at southbound frontage road and Bonnie and south of Loop 288. Continue with bridge 4-braided ramp northbound frontage road before US 380. Start building permanent
retaining wall on southbound frontage road before US 380 north of US 380. Finish temporary signal installation at Oak and Bonnie Brae and activate US 380 temporary intersection signals. Place overhead temporary signs throughout project. Finish retaining walls on southbound frontage road north of US 380 and northbound before Merge. Continue drill shafts and columns for direct connector from I-35E from I-35W. Start drill shafts and columns for off-ramp from I-35W northbound to
Oak Street. Fixing potholes through-out project.
Narrative description of last month’s activities: Continue with earthwork and excavation at I-35W future off-ramp for
FM 1515. Continue retaining wall at I-35W future off-ramp for FM 1515. Continue temporary shoring wall for detour along northbound frontage road from Bonnie Brae to Oak Street and southbound I-35 Oak Street to Airport Road. Continue placing temporary detour at 8 locations including southbound main lanes, northbound frontage, and southbound frontage road. Place drainage along southbound frontage I-35E from Bonnie Brae to North Texas. Continue placing drainage from Scripture to US 380 and US 380 to Loop 288. Placing culvert at Bonnie Brae and south of Loop 288. Continue with braided ramp northbound frontage road before US 380. Start building permanent retaining wall southbound frontage road before US 380
north of US 380. Finish temporary signals at US 380, Oak, and Bonnie Brae and activate temporary US 380 intersection signals. Placed permanent asphalt at southbound frontage road south of Loop 288, ramps for Bonnie Brae, and northbound frontage road. Place overhead temporary signs throughout project. Finish retaining wall southbound frontage road north of US 380 and northbound before I-35 Merge. Continue drill shafts and columns for direct connector.
Narrative description of activities planned for next month: Continue with earthwork and excavation with I-35W future off-ramp for FM 1515. Continue retaining wall at I-35W future off-ramp for FM 1515. Continue temporary shoring wall for detour along northbound frontage road from Bonnie Brae to Oak Street and southbound frontage road from Oak Street to Airport Road. Continue placing temporary detour at 10 locations including southbound main lanes, I-35W, northbound frontage roads, and southbound frontage roads. Continue placing drainage from Scripture to US 380 and US 380 to Loop 288.Continue bridge ramp on northbound frontage roads before US 380. Continue permanent retaining wall southboundfrontage road before US 380. Continue permanent concrete at southbound frontage road south of Loop 288, ramp for BonnieBrae, and northbound frontage road. Continue overhead temporary signs throughout project. Finish retaining walls.Continue bridges for direct connector and off-ramp at I-35W to Oak Street.
Traffic issues: Nightly lane closures. Temporary one-lane frontage road until off-ramp for Bonnie Brae is completed.
Plans for changes in traffic patterns: None
Item(s) of work currently controlling project completion: Off ramps, bridges, and walls.
Other items of significance: None
10
City of Denton Transportation Update Prepared by:
May 2025 7
Current Activity:
•PS&E: LTRA updated the plan set to the 2024 TxDOT Specifications and included additionalsheets and quantities requested by TxDOT. LTRA submitted final plan set to TxDOT.
•Utilities: The status of utilities in conflict is listed below.
o Utilities currently clear of construction: Atmos Gas (Distribution), AT&T, CoServ Gas,City of Denton Water, City of Denton Wastewater, NGG, Oncor, and United PrivateNetworks.o Utilities that are currently relocating: Astound (Grande), Brightspeed/CenturyLink,
Charter/Spectrum, DISD, DME, Frontier, Lumen/Level 3, and Zayo.
o Utilities that are pending relocation: None.
o Utilities that are critical path: DME is placing new poles needed for Charter and Frontierto complete.
I-35E/Mayhill
CSJ: 0196-01-109 Schematic Approval: February 2011
Limits: I-35E intersection with Mayhill from
Pockrus Page Rd to Loop 288 Environmental Clearance: January 31, 2012
Length: 1.912 miles ROW Acquisition Completed: November 2022
Description: Reconstruct interchange at Mayhill and
I-35E and existing 4-lane frontage roads Utility Relocations Complete: August 2025
Est. Construction Cost: $139,130,349 City of Denton Utility
Relocations Completed: February 2024
Funding: $139,130,349 CAT 2: $129,130,349
CAT 4: $10,000,000
100% Plans: November 2024
Firm & Key Contact: LTRA, Tyler Martin Let Date: June 2025
TxDOT Project Manager: Chaikou Bah Construction Start: *
11
City of Denton Transportation Update Prepared by:
May 2025 8
Current Activity:
•PS&E: WSP continues addressing TxDOT comments to 95% plan set and is working toward
completion of final plan set.
•ROW: There are 58 parcels to acquire. There are: 3 parcels in ED and 55 parcels acquired. ROWacquisition has been placed on hold due to District budgetary constraints.
•Utilities: The status of utilities in conflict is listed below.o Utilities that are clear of construction: DME Transmission and UTRWD.o Utilities that are currently relocating: None.
o Utilities that are pending relocations: Atmos, CoServ Electric, DME Distribution,Fiberlight, Frontier, Fiberlight, Lumen, and Zayo.o Utilities that are critical path: CoServ pole placement design and placement is needed fortelecoms to finalize their design.
I-35W Frontage Roads Middle
CSJ: 0081-13-071 Schematic Approval: March 20, 2020
Limits: From 0.7 miles south of FM 407 to FM 2449 Environmental Clearance: June 30, 2020 Length: 6.76 miles
Project Description: Construct frontage roads ROW Acquisition Complete: June 2026
Est. Construction Cost: $446,891,327 Utility Relocations Complete: December 2027
Funding:
$213,024,000
CAT 2: $24,537,247
CAT 12: $188,486,753
100% Plans: December 2025
Firm: WSP Ready to Let Date: December 2027
TxDOT Contact: Gutema Gebriel Let Date: *
12
City of Denton Transportation Update Prepared by:
May 2025 9
Current Status:
•ROW: For RCSJ 2250-02-023, there
are 19 parcels to acquire. There are: 2
parcels in ED and 17 parcels in
possession. For RCSJ 2250-02-024,there are 20 parcels to acquire. Thereare: 5 parcels in negotiations and 15parcels in possession.
•ROW acquisition efforts are on hold dueto District budgetary constraints.
•PS&E: CP&Y updated PBLR for final
submittal.
•CP&Y updated Exhibit A and madefinal submittal on September 30, 2024.
•The 95% PS&E plan set submittal was
made on September 3, 2024. Thecomment resolution meeting was heldon January 28, 2025. CP&Y continuedaddressing comments and workingtoward final submittal.
•TxDOT requested revised trafficnumbers; CP&Y awaiting new pavementdesign to finalize submittal.
•Bi-weekly coordination meetings underway.
•Utilities: SUE Level A submittal was made on October 11, 2024. Completed two Level A testholes for gas pipeline crossing per TxDOT request. Investigated conflict with Enterprise andAtmos Gas lines.
Loop 288 West Frontage Roads
CSJ: 2250-00-013 (from I-35 to US 380)
2250-00-032 (from US 380 to I-35W) Schematic Approval: March 20, 2020
Limits: From I-35 to I-35W Environmental Clearance: September 28, 2020 Length: 9.0 miles
Description: Construct frontage roads ROW Acquisition Complete: December 2025
Estimated Construction
Cost:
$227,423,354
-013: $95,315,990
-032: $132,107,364
Utility Relocations Complete: April 2026
Funding: $3,000,000 CAT 3
$1,000,000 CAT 7 100% Plans: June 2025
Firm & Key Contact: CP&Y, Tom Cochill & Jacob Roberts Ready to Let Date: April 2026
TxDOT Project Manager: Gutema Gebriel Let Date: *
13
City of Denton Transportation Update Prepared by:
May 2025 10
Current Activity:
•PS&E: Westwood submitted revised schematic on March 28, 2025. Westwood completed 100%review comments on May 2, 2025.
•Westwood submitted drainage report to TxDOT for review; working on additional drainage reportrevisions according to comments received from TxDOT.
•The 95% SUE plans and conflict matrix sent to TxDOT on May 1, 2025.
•ROW footprint meeting set for May 1, 2025.
•Westwood met with City of Denton on May 1, 2025; discussing new developments and revisions inschematic.
•Environmental: Tentative public hearing date is April 24, 2025. TxDOT approved project for anEnvironmental Assessment (EA). Westwood is working on Environmental Assessment and
Technical Reports.
Loop 288 East-US 380 Connector
CSJ: 2250-02-025; 0135-10-066 Schematic Approval: June 2025
Limits: from I-35 to US 380 east of Geesling Road Environmental Clearance: December 2025 Length: 8 miles
Project Description:
Construct Loop 288 frontage roads and grade
separations and an improved connector to US
380
ROW Acquisition Completion: *
Estimated Const. Cost: $1.262 billion Utility Relocations Completion: *
Funding: * 100% Plans: *
Firm & Key Contact: Westwood, Mark Schluter, Mark Zoellner Ready to Let Date: *
TxDOT PM: Stephen Endres Let Date: *
14
City of Denton Transportation Update Prepared by:
May 2025 11
Current Activity:
•PS&E: The segment between US 77 and Loop 288 has been added to Loop 288 East contractwith Westwood.
Bonnie Brae Segment 7
CSJ: * Schematic Approval: June 2025
Limits: From US 77 to Loop 288 Environmental Clearance: December 2025
Length: 0.2 miles ROW Acquisition Complete: *
Description: Extension of Bonnie Brae north of US 77 Utility Relocations Complete: *
Est. Construction Cost: * 100% Plans: *
Funding: * Ready to Let Date: *
Firm & Key Contact: Westwood, Mark Schluter, Mark Zoellner Let Date: *
TxDOT Project Manager: Stephen Endres Construction Start: *
15
City of Denton Transportation Update Prepared by:
May 2025 12
Current Activity:
•PS&E: LTRA updated plans to the 2024 TxDOT Specifications and submitted the final planset on June 28, 2024. Plans have been shelved until letting.
•Exhibit A: LTRA submitted new Exhibit A for CPKC approval.
•Utilities: The status of utilities in conflict is listed below.
o Utilities that are clear of construction: none.o Utilities that are currently relocating: none.
o Utilities that are pending relocation: AT&T, Atmos, Brightspeed/CenturyLink,
Charter/Spectrum, City of Denton Water/Wastewater, DME Distribution, Lumen,
MCI/Verizon, and UPN.
o Utilities that are critical path: City Water needs to be placed prior to Atmos. DMEpoles are needed for telecoms to begin.
FM 1515
CSJ: 1951-01-011 Schematic Re-approval: October 13, 2021
Limits: From Bonnie Brae to Masch Branch Road Environmental Approval: August 4, 2020
Length: 2.096 miles Environmental Re-eval: March 15, 2022
Description: Widen existing 2-lane rural section to a six-
lane divided urban roadway ROW Acquisition Complete: July 2023
Est. Construction Cost: $69,484,709 Utility Relocations Complete: January 2026
Funding: $500,000 CAT 7 100% Plans: June 2024
Firm & Key Contact: LTRA, Tyler Martin Ready to Let Date: January 2026
TxDOT Project Manager: Bryan Esmaili-Doki Let Date: *
16
City of Denton Transportation Update Prepared by:
May 2025 13
Current Activity:
•PS&E: Halff submitted final plan set to TxDOT on March 11, 2025. TxDOT requested minor
revisions to plan set. Halff resubmitted 100% PS&E plan set on May 1, 2025.
•Halff submitted BNSF Exhibit A on September 24, 2024.
•Utilities: The status of utilities in conflict is listed below.
o Utilities that are clear of construction: None.
o Utilities that are currently relocating: AT&T, Atmos Distribution, CoServ Electric, andOncor.o Utilities that are pending relocations: Altice, Atmos, Brightspeed, City of DentonSewer, City of Krum Water/Sewer, Fiberlight, and Zayo.
o Utilities that are critical path: City of Krum Water/Sewer; Atmos line resolution to
avoid adjusting, and CoServ and Oncor poles need to be placed for telecoms.
FM 1173
CSJ: 1059-01-047; 1059-02-002 Schematic Approval: March 20, 2020
Limits: From I-35E to FM 156 Environmental Clearance: August 26, 2021 Length: 3.613 miles
Description: Widen and realign to 4/6-lane divided
urban road ROW Acquisition Completed: September 2023
Est. Construction Cost:
$125,852,145
-047: $62,892,803
-002: $62,959,342
Utility Relocations Complete: June 2026
Funding: * 100% Plans: May 2025
Firm & Key Contact: Halff Associates, Adam Bazar Ready to Let Date: June 2026
TxDOT PM: Kwan Lam Let Date: *
17
City of Denton Transportation Update Prepared by:
May 2025 14
Current Activity:
•Design: LJA submitted the 30% schematic on March 12, 2025. TxDOT provided comments to
TxDOT; LJA is reviewing and responding.
•LJA is working toward completion of 60% submittal.
•LJA continues coordination with NCTCOG, TxDOT, USACE, and other agencies.
•LJA continues identifying developments adjacent to proposed Outer Loop alignment.
•LJA is coordinating with survey to identify existing culvert locations and sizes.
•LJA is reviewing IAJR comments. Received 2050 traffic projections draft model from NCTCOG.
•Utilities: LJA continues evaluating transmission level utilities within study area and gathering
information near refined alignments and coordinating with entities. LJA continues developingLevel D map. LJA is coordinating and identifying areas to perform Level B SUE.
•Environmental: Evaluating easements and TxDOT property near USACE property. Reviewingadditional constraints and areas of concern. Tracking right-of-entry responses. Ongoing field
work in areas where right-of-entry has been obtained. LJA is reviewing and responding tocomments received regarding various environmental technical reports.
•Other: Project website is available: www.DentonCountyOuterLoop.com.
•Public Involvement: Anticipate a public meeting to be held in September 2025.
Outer Loop
CSJ: 0918-46-341 Schematic Approval: March 2026
Limits: From I-35 to the DNT at the Denton County
Line Environmental Clearance: September 2026
Length: 23 miles ROW Acquisition Complete: *
Description: Construct a six-lane controlled access
freeway with continuous frontage roads Utility Relocations Complete: *
Est. Construction Cost: $1,547,212,128 100% Plans: *
Funding: * Ready to Let Date: *
Firm & Key Contact: LJA, Tony Kimmey Let Date: *
TxDOT Project Manager: Liang Ding Construction Start: *
18
City of Denton Transportation Update Prepared by:
May 2025 15
•AADT – Annual Average Daily Traffic
•AFA – Advanced Funding Agreement
•ARPA – Archeological Resources Protection Act
•CE – Categorical Exclusion (environmental clearance process for projects that do not involve significantenvironmental impacts)
•CLOMR – (FEMA’s) Conditional Letter of Map Revision
•Conformity – Federal requirement in nonattainment areas to conduct air quality analysis on projects,programs, and policies identified in transportation plans, transportation improvement programs,federally funded projects, or projects requiring federal approval
•CSJ – (TxDOT’s) Control Section Job Number
•DCC – Design Concept Conference
•EA – Environmental Assessment
•ED – Eminent Domain
•EIS – Environmental Impact Statement
•EPIC – Environmental Permits, Issues, and Commitments
•ESAL – Equivalent Single Axle Load (TxDOT design calculation)
•FONSI – Finding of No Significant Impact
•IAJR – Interstate Access Justification Request
•ICA – Interlocal Cooperative Agreement
•IFP – Initial Financial Plan
•Let – Official date of receipt and opening of bids
•MAPO – Meeting with Affected Property Owners
•MPO – Metropolitan Planning Organization
•MTP – Metropolitan Transportation Plan
•NCTCOG – North Central Texas Council of Governments
•NEPA – National Environmental Policy Act
•NOPC – Notice of Proposed Construction
•NTTA – North Texas Toll Authority
•PBLR – Preliminary Bridge Layout Review
•PS&E – Plans Specifications and Estimate
•PUA – Possession and Use Agreement
•ROW – Right-of-Way
•RTC – Regional Transportation Council
•RTL – Ready to Let (date project is clear for construction but lacks funding for actual let)
•RTR – Regional Toll Revenue (funds resulting from certain toll/managed lane projects in DFW region)
•RULIS – Right-of-Way, Utilities, Leasing, and Information System
•STBG – Surface Transportation Block Grant
•STIP – Statewide Transportation Improvement Program
•SUE – Subsurface Utility Engineering
•SW3P – Storm Water Pollution Prevention Plan
•TCP – Traffic Control Plan
•TIA – Time Impact Analysis
•TPP – Transportation Planning and Programming
•TPWD – Texas Parks & Wildlife Department
•TTC – Texas Transportation Commission
•TxDOT – Texas Department of Transportation
•UTP – Unified Transportation Program
•VE – Value Engineering
Glossary of Acronyms
19
City of Denton Transportation Update Prepared by:
May 2025 16
•CAT 1: Preventive Maintenance and Rehabilitation
•CAT 2: Metro and Urban Area Corridor Projects / NCTCOG
•CAT 3: Non-Traditionally Funded Transportation Projects
•CAT 4: Statewide Connectivity Corridor Projects
•CAT 5: Congestion Mitigation and Air Quality Improvement / NCTCOG
•CAT 6: Structures Replacement and Rehabilitation (Bridge)
•CAT 7: Metropolitan Mobility and Rehabilitation / NCTCOG
•CAT 8: Safety Projects
•CAT 9: Transportation Alternatives
•CAT 10: Supplemental Transportation Projects
•CAT 11: District Discretionary
•CAT 12: Strategic Priority
TxDOT Funding Categories
20
City of Denton Transportation Update Prepared by:
May 2025 17
Denton City Limits
21
22
Friday Report - Council RequestsSummary of RequestCouncil Member Requestor Date Received Staff AssignedDepartmentCommentsStatus1Alley maintenanceCouncil Member Byrd MayorHudspeth05/29/25Antonio PuenteDMEReferred to staff.2Green space behind Target/Home Depot Mayor Hudspeth05/28/25Gary Packan, Jesse Kent, Tony SalasCommunity Services Police Parks Referred to staff3Code Violation Request for Additional Time Mayor Hudspeth05/27/25Jesse KentCommunity ServicesReferred to staf.4Police Data InquiryCouncil Member Byrd05/27/25Jessica Robledo, Tony SalasPoliceReferred to staff.5Sidewalk repair Wellington OaksCouncil Member Holland05/20/25Jeremy Wilks, Scott McDonaldDevelopment Services Public Works-TrafficStaff inspected the site.Updated CM.Page 1 of 1Exported on May 30, 2025 1:55:12 PM PDT23
Meeting Calendar
City of Denton City Hall
215 E. McKinney St.
Denton, Texas 76201
www.cityofdenton.com
Criteria : Begin Date: 6/2/2025, End Date: 9/5/2025
Date Time Meeting LocationMeeting Body
June 2025
6/2/2025 6:00 PM Parks, Recreation and Beautification
Board
Civic Center Community Room
6/3/2025 3:00 PM City Council Council Work Session Room
&
Council Chambers
6/5/2025 8:00 AM Agenda Committee Cancelled
6/5/2025 8:30 AM Downtown Economic Development
Committee
CANCELLED
6/9/2025 9:00 AM Public Utilities Board Council Work Session Room
6/9/2025 3:00 PM Development Code Review Committee Development Services Center
6/9/2025 5:30 PM Board of Ethics Council Work Session Room
6/9/2025 5:30 PM Historic Landmark Commission Development Service Center
6/9/2025 5:30 PM Library Board North Branch Library
6/11/2025 11:00 AM Economic Development Partnership
Board
Development Service Center
6/11/2025 12:30 PM Tax Increment Reinvestment Zone
Number Two Board
Development Service Center
6/11/2025 3:00 PM Airport Advisory Board Airport Terminal Meeting Room
6/11/2025 5:00 PM Planning and Zoning Commission Council Work Session Room
&
Council Chambers
6/12/2025 3:00 PM Health & Building Standards
Commission
Development Service Center
6/13/2025 12:00 PM Community Services Advisory
Committee
Development Service Center
6/13/2025 5:00 PM City Council Council Work Session Room
&
Council Chambers
6/17/2025 12:00 PM City Council Council Work Session Room
&
Council Chambers
6/17/2025 2:00 PM City Council Council Work Session Room
&
Council Chambers
Page 1City of Denton Printed on 5/29/202524
Date Time Meeting LocationMeeting Body
Meeting Calendar continued...
6/23/2025 9:00 AM Public Utilities Board Council Work Session Room
6/23/2025 3:00 PM Development Code Review Committee Development Services Center
6/23/2025 5:30 PM Zoning Board of Adjustment Development Service Center
6/25/2025 10:00 AM Mobility Committee Council Work Session Room
6/25/2025 5:00 PM Planning and Zoning Commission Council Work Session Room
&
Council Chambers
6/25/2025 6:00 PM Denton Police Department Chief of
Police Advisory Board
Public Safety Training Center
719 E. Hickory Street
Denton, Texas 76205
6/27/2025 9:00 AM Community Partnership Committee City Council Work Session Room
6/27/2025 1:00 PM Sustainability Framework Advisory
Committee
City Council Work Session Room
July 2025
7/3/2025 8:00 AM Agenda Committee Council Work Session Room
7/7/2025 6:00 PM Parks, Recreation and Beautification
Board
Civic Center Community Room
7/9/2025 Animal Shelter Advisory Committee Animal Services Training Room
7/9/2025 10:00 AM Animal Shelter Advisory Committee Animal Services Training Room
7/10/2025 Health & Building Standards
Commission
Development Service Center
7/11/2025 Zoning Board of Adjustment Council Work Session Room
7/14/2025 9:00 AM Public Utilities Board Council Work Session Room
7/14/2025 3:00 PM Development Code Review Committee Development Services Center
7/14/2025 5:30 PM Board of Ethics Council Work Session Room
7/14/2025 5:30 PM Historic Landmark Commission Development Service Center
7/14/2025 5:30 PM Library Board South Branch Library
7/15/2025 2:00 PM City Council Council Work Session Room
&
Council Chambers
7/17/2025 3:00 PM Committee on Persons with Disabilities Development Service Center
7/22/2025 2:00 PM City Council Council Work Session Room
&
Council Chambers
7/23/2025 12:00 PM Tax Increment Reinvestment Zone
Number One Board
Development Service Center
7/23/2025 5:00 PM Planning and Zoning Commission Council Work Session Room
&
Council Chambers
Page 2City of Denton Printed on 5/29/2025
25
Date Time Meeting LocationMeeting Body
Meeting Calendar continued...
7/25/2025 9:00 AM Community Partnership Committee City Council Work Session Room
7/25/2025 1:00 PM Sustainability Framework Advisory
Committee
City Council Work Session Room
7/28/2025 9:00 AM Public Utilities Board Council Work Session Room
7/28/2025 5:30 PM Zoning Board of Adjustment Development Service Center
7/30/2025 10:00 AM Mobility Committee Council Work Session Room
August 2025
8/4/2025 6:00 PM Parks, Recreation and Beautification
Board
Civic Center Community Room
8/5/2025 2:00 PM City Council Council Work Session Room
&
Council Chambers
8/7/2025 8:00 AM Agenda Committee Council Work Session Room
8/7/2025 8:30 AM Downtown Economic Development
Committee
Development Service Center
8/7/2025 4:00 PM Public Art Committee Civic Center Community Room
8/8/2025 12:00 PM Community Services Advisory
Committee
Development Service Center
8/9/2025 8:00 AM City Council Council Work Session Room
&
Council Chambers
8/11/2025 9:00 AM Public Utilities Board Council Work Session Room
8/11/2025 3:00 PM Development Code Review Committee Development Services Center
8/11/2025 5:30 PM Board of Ethics Council Work Session Room
8/11/2025 5:30 PM Historic Landmark Commission Development Service Center
8/11/2025 5:30 PM Library Board Emily Fowler Central Library
8/13/2025 11:00 AM Economic Development Partnership
Board
Development Service Center
8/13/2025 3:00 PM Airport Advisory Board Airport Terminal Meeting Room
8/13/2025 5:00 PM Planning and Zoning Commission Council Work Session Room
&
Council Chambers
8/14/2025 3:00 PM Health & Building Standards
Commission
Development Service Center
8/19/2025 2:00 PM City Council Council Work Session Room
&
Council Chambers
8/22/2025 9:00 AM Community Partnership Committee City Council Work Session Room
8/25/2025 9:00 AM Public Utilities Board Council Work Session Room
Page 3City of Denton Printed on 5/29/2025
26
Date Time Meeting LocationMeeting Body
Meeting Calendar continued...
8/25/2025 3:00 PM Development Code Review Committee Development Services Center
8/25/2025 5:30 PM Zoning Board of Adjustment Development Service Center
8/27/2025 10:00 AM Mobility Committee Council Work Session Room
8/27/2025 5:00 PM Planning and Zoning Commission Council Work Session Room
&
Council Chambers
September 2025
9/4/2025 8:00 AM Agenda Committee Council Work Session Room
9/5/2025 1:00 PM Bond Oversight Committee Development Service Center
Page 4City of Denton Printed on 5/29/2025
27
Meeting Date Item Legistar ID Departments Involved Type Estimated Time
A. Denton Renewable Resource Plan 24-1910 Denton Municipal Electric City Business 1:00
B. Special Events Fee Update 25-766 Finance City Business 1:00
D. Two Minute Pitch:25-027 City Manager's Office Council Request 0:30
Closed Meeting Item(s): Legal (if any)City Business 0:30
Total Est. Time: 3:00
Other Major Items for Meeting:
Closed Meeting Item(s): Legal (if any)City Business 0:30
Total Est. Time: 0:30
Other Major Items for Meeting:
A. Budget Update - Current Year, and Fiscal Year 2025-2026 Forecast 24-2616 Finance City Business 1:00
B. Climate Action Plan Update 25-421 Environmental Services City Business 0:45
C. Legislative Session Recap 25-1043 City Manager's Office City Business 0:30
D. City Council Committee Assignments 25-1026 City Secretary's Office City Business 0:45
E. Two Minute Pitch:25-028 City Manager's Office Council Request 0:30
Closed Meeting Item(s): Legal (if any)City Business 0:30
Total Est. Time: 4:00
Other Major Items for Meeting:
A. Audit of Public Works Maintenance 25-338 Internal Audit City Business 0:30
B. Audit of Parks Management and Planning 25-340 Internal Audit City Business 0:30
C. Capital Improvement Program Fiscal Year 2025-2026 24-2617 Finance City Business 1:00
D. Countywide Vote Centers TBD City Secretary's Office Council Request 0:30
E. Two Minute Pitch:25-029 City Manager's Office Council Request 0:30
Closed Meeting Item(s): Legal (if any)City Business 0:30
Total Est. Time: 3:30
Other Major Items for Meeting:
A. Utility Budgets and Rates Fiscal Year 2025-2026 24-2618 Finance City Business 1:00
B. Water Master Plan 25-363 Water City Business 0:45
C. Fair Chance Hiring Ordinance TBD City Manager's Office Council Request 1:00
D. EV and Solar Ready Building Code TBD Development Services Council Request 0:30
E. Two Minute Pitch:25-030 City Manager's Office Council Request 0:30
Closed Meeting Item(s): Legal (if any)City Business 0:30
Total Est. Time: 4:15
Other Major Items for Meeting:
A. East Hickory Street Parking TBD City Manager's Office Council Request 0:30
B. Two Minute Pitch:25-031 City Manager's Office Council Request 0:30
Closed Meeting Item(s): Council Appointed Position Performance Reviews: City Manager and City
Attorney Legal (if any)City Business 0:30
Total Est. Time: 1:30
Other Major Items for Meeting:
A. 2025-26 City Manager’s Proposed Budget, Capital Improvement Program, and Five-Year Financial
Forecast.24-2619 Finance City Business 4:00
Closed Meeting Item(s): Legal (if any)City Business 0:30
Total Est. Time: 4:30
Other Major Items for Meeting:
A. Fiscal Year 2025-26 City Manager's Proposed Budget, Capital Improvement Program, and Five-Year
Financial Forecast 24-2620 Finance City Business 1:00
B. Animal Services Audit Follow Up TBA Internal Audit City Business 0:30
C. Two Minute Pitch:25-032 City Manager's Office Council Request 0:30
Closed Meeting Item(s): Council Appointed Position Performance Reviews: City Auditor and Municipal
Judge Legal (if any)City Business 0:30
Total Est. Time: 2:30
Other Major Items for Meeting:
A. Inclement Weather Policy TBD City Manager's Office City Business 1:00
B. Budget Update TBD Finance City Business 1:00
C. Two Minute Pitch:25-033 City Manager's Office Council Request 0:30
Closed Meeting Item(s): Legal (if any)City Business 0:30
Total Est. Time: 3:00
Other Major Items for Meeting:
A. Budget Update TBD Finance City Business 1:00
B. Two Minute Pitch:25-034 City Manager's Office Council Request 0:30
Closed Meeting Item(s): Legal (if any)City Business 0:30
Total Est. Time: 2:00
Other Major Items for Meeting:
A. Two Minute Pitch:25-035 City Manager's Office Council Request 0:30
Closed Meeting Item(s): Legal (if any)City Business 0:30
Total Est. Time: 1:00
Other Major Items for Meeting:
Item Date Approved Department Next Step Requestor
Board of Ethics develop guidance for interactions with external partners 6/18/2024 Internal Audit Work Session CM Beck
Rooftop and wall gardens and solar panels on City buildings 12/3/2024 Facilities Management Agenda Committee CM Beck
June 3
Work Session (@3:00 p.m.)
Regular Called Meeting (@6:30 p.m.)
July 22
Work Session (@2:00 p.m.)
Special Called Meeting (Upon Conclusion of
the Work Session)
August 5
Work Session (@2:00 p.m.)
Regular Called Meeting (6:30 p.m.)
September 9
Work Session (@2:00 p.m.)
Special Called Meeting (Upon conclusion of
the Work Session)
August 19
Work Session (@2:00 p.m.)
Regular Called Meeting (6:30 p.m.)
September 16
Work Session (@2:00 p.m.)
Regular Called Meeting (@6:30 p.m.)
September 30
Work Session (@2:00 p.m.)
Special Called Meeting (Upon conclusion of
the Work Session)
Approved Council Pitches to be Scheduled
Council Priorities and Significant Work Plan Items
to be Scheduled
Tentative Work Session Topics and Meeting Information
Updated: May 30, 2025
June 17
Special Called Meeting - Canvassing of Runoff
(@12:00 p.m.)
Reception (@12:30 p.m.)
July 15
Work Session (@2:00 p.m.)
Regular Called Meeting (@6:30 p.m.)
August 9
Saturday Budget Workshop (8:00 a.m.)
June 17
Work Session (@2:00 p.m.)
Regular Called Meeting (@6:30 p.m.)
*This is for planning purposes only. Dates are subject to change.28
1 Street Closure Report: Upcoming ClosuresSCR June 2nd - 8thStreet/ IntersectionFromToClosure StartDateClosure EndDateDescriptionDepartmentDepartment Contact Closure Type1Bonnie Brae St SWillowwood StParvin St06/09/25 10/10/25 Installation of drainage infrastructure,embankment work in advance of streetwidening. (Access to Natl Wholesale &residents only)EngineeringRobin DavisFull Closure2La Mirada (1500)Manten BlvdZilda Way06/09/25 07/04/25 Concrete Panel RepairStreetsRoy San MiguelLane Closure3Ponder StOak StPanhandle St06/19/25 04/27/26 Utility installations and pavement replacement EngineeringMegan DavidsonFull ClosureExported on May 30, 2025 11:41:53 AM CDT29
2 Street Closure Report: Current ClosuresStreet/ IntersectionFromToClosure StartDateClosure EndDateDescriptionDepartmentDepartment Contact Closure Type1Aileen StPanhandle StBroadway St09/27/24 06/30/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure2Alice StSunset StUniversity Dr (US 380)05/27/25 06/06/25 Utility installations andpavement replacement.EngineeringScott FettigRolling Closure3Alice StPanhandle StCrescent St05/02/25 12/05/25 Utility installations andpavement replacement.EngineeringMegan DavidsonFull Closure4Ave ACollins StEagle Dr10/08/24 06/30/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure5Ave AEagle DrHighland St02/03/25 07/01/25 Utility installations andpavement replacement.EngineeringScott FettigRolling Closure6Ave BFannin StMargie St11/22/24 06/30/25 Pavement replacement EngineeringScott FettigFull Closure7Ave DChestnut StMulberry St05/12/25 08/15/25 Utility installations andpavement replacement.EngineeringMegan DavidsonFull Closure8Ave GPrairie StLousie St03/13/25 06/27/25 Utility installations andpavement replacementEngineeringMegan DavidsonFull Closure9Bell AveUniversity Dr (Hwy 380)Texas St05/12/25 06/09/25 Waterline tap and newinstallationAtmos DrainageEngineering PrivateDevelopment Public WorksInspections Streets TrafficTXDoT Water WastewaterChristopher YanezFull Closure10Bell Ave N (1000)Chappel DrTexas St05/12/25 06/09/25 Waterline tap and newinstallationWaterChristopher YanezFull Closure11Bernard StLindsey StFannin St08/26/24 06/20/25 Utility installations andpavement replacement.EngineeringScott FettigRolling Closure12Bonnie Brae StAirport Rd (FM 1515)Walt Parker Dr (Main Stadium Dr) 01/06/25 06/30/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure13Cactus CirYucca Dr(End of street) Cul de sac04/28/25 09/02/25 Utilities and PavementreplacementEngineeringDante HaleFull Closure14Camelot StHercules LnStuart Rd04/28/25 07/01/25 Utilities and PavementreplacementEngineeringDante HaleRolling Closure15Chestnut StAve CAve D05/12/25 08/15/25 Utility installations andpavement replacement.EngineeringMegan DavidsonFull Closure16Clover LnRobinwood LnGlenwood Ln11/12/24 07/12/25 Full Road Reconstruction EngineeringSheldon GatewoodFull Closure17Collins StAve ABernard St08/26/24 06/20/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure18Congress StPonder StCoit St02/03/25 07/01/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure19Congress StPonder StCarroll Blvd03/31/25 07/04/25 Utility constructionEngineeringMegan DavidsonRolling Closure20Cornell LnUniversity Dr WAmherst Dr06/02/25 06/20/25 Water TapsPublic Works Inspections Alexander CervantesLane Closure21Crescent StCarroll BlvdBolivar St01/24/25 07/01/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure22Crescent StAileen StMalone St05/21/25 07/21/25 Utility installations andpavement replacement.EngineeringMegan DavidsonFull Closure23Denton StHickory StCongress St06/02/25 11/05/25 Utility installations andpavement replacementEngineeringMegan DavidsonFull Closure24Eagle DrAve CAve A03/17/25 06/13/25 Using it or an entrance due toelevation changes in the jobsiteit is the only way to get into thesitePublic Works Inspections Collin ColeLane Closure25Egan StCarroll BlvdBolivar St05/07/25 09/10/25 Utility installations andpavement replacement.EngineeringMegan DavidsonFull Closure26Emery StAlice StDead End (West of Fulton)02/03/25 07/01/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure27Fry StOak StHickory St04/28/25 06/06/25 Mastec relocating gas lines Public Works Inspections Stephany TrammellRolling Closure28Fulton StCordell StEmery St02/03/25 07/01/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure29Hickory Creek RdRiverpass DrCountry Club Rd (FM 1830) 03/13/23 12/31/26 Bridge InstallationEngineeringTracy BeckFull Closure30Hilltop Rdat Country Club Road (FM 1830)05/27/25 09/30/25 Hilltop Road at Country ClubRoad will be reconstructed (newdrainage, road, etc.) and newnorthbound right turn lane willbe added to Country Club RoadEngineeringTracy BeckFull Closure31Hobson LnForrestridge DrCountry Club Rd05/08/25 06/06/25 Utility work and turn laneconstruction on HobsonPublic Works Inspections Gavin PetnerFull Closure Exported on May 30, 2025 11:42:06 AM CDT30
Street/ IntersectionFromToClosure StartDateClosure EndDateDescriptionDepartmentDepartment Contact Closure Type32Huisache StAspen DrYucca Dr04/09/25 08/08/25 Utilities and PavementreplacementEngineeringDante HaleRolling Closure33Jim Christal RdMasch Branch Rd@ Intersection03/07/25 06/06/25 Adding 2 Lanes E/W on JimChristal: Adding a turn Lane onMasch BranchPublic Works Inspections Kirk WinterLane Closure34Juno LnAtlas DrStuart Dr04/09/25 08/08/25 Utility installations andpavement replacement.EngineeringScott FettigRolling Closure35Margie StAve AAve B11/01/24 06/20/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure36Mistywood LnRobinwood LnGlenwood Ln04/28/25 07/12/25 Voids undergroundOtherSheldon GatewoodFull Closure37Morse StLoop 288Mayhill Rd12/02/24 06/27/25 Water Line Replacement andRoad ReconstructionPublic Works InspectionsStreets WaterKristine StewartLane Closure38Mounts AveCongress St WHaynes St03/21/25 06/27/25 Utility installations andpavement replacementEngineeringMegan DavidsonFull Closure39Mulberry StElm StCarroll Blvd03/17/25 06/13/25 Water/Wastewater connections Public Works Inspections Stephany TrammellFull Closure40Mulberry StWelch StBernard St11/29/24 06/30/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure41Normal StOak StScripture St05/08/25 09/05/25 Utility installations andpavement replacement.EngineeringMegan Davidson42Northridge StHinkle DrBolivar St04/16/25 04/20/26 Utilities and PavementreplacementEngineeringDante HaleRolling Closure43Oak StCarroll BlvdFry St04/21/25 06/13/25 Mastec relocating gas lines Public Works Inspections Stephany TrammellRolling Closure44Oak StWelch StAve C04/28/25 07/11/25 Mastec relocating gas lines Public Works Inspections Stephany TrammellRolling Closure45Oak St E (109)Austin Stat Intersection05/19/25 07/04/25 ADA / Sidewalk Work atIntersectionStreetsRoy San MiguelLane Closure46Ocean DrAtlantic DrNautical Ln04/14/25 06/18/25 Sanitary Sewer installPrivate DevelopmentGavin PetnerFull Closure47Parvin St@ Bonnie Brae St06/04/25 06/06/25 Installation of storm draininfrastructure crossing Parvin -(No access to Bonnie Brae fromParvin)EngineeringRobin DavisFull Closure48Pershing DrAtlas DrStuart Rd05/08/25 12/15/25 Utilities and PavementreplacementEngineeringDante HaleFull Closure49Ponder AveOak St WBroadway St06/02/25 12/31/25 Utility installations andpavement replacement.EngineeringScott FettigRolling Closure50Prairie StWelch StBernard St03/13/25 06/27/25 Utility installationsEngineeringMegan DavidsonFull Closure51Precision DrAirport RdUNT Library Annex04/01/25 07/31/25 ReconstructionEngineering OtherGio PineiroFull Closure52Redstone RdHercules LnNeptune Dr05/05/25 06/12/25 Utilities and PavementreplacementEngineeringDante HaleFull Closure53Riney RdBonnie Brae StHardaway Rd03/08/25 08/01/25 Contractor to install 12-inchwaterline to provide water to thenew DISD elementary schoolEngineeringJesus PerezFull Closure54Robinwood LnLive OakKayewood Dr01/27/25 06/30/25 Road reconstruction (Millingand C/G Removal, Stabilization)EngineeringSheldon GatewoodFull Closure55Robinwood LnEmerson LnLive Oak St11/12/24 07/12/25 Full Road Reconstruction EngineeringSheldon GatewoodFull Closure56Scripture StJagoe StPonder St03/04/25 10/17/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure57Selene DrNeptune DrStuart Rd06/04/25 11/28/25EngineeringScott FettigFull Closure58Sunset StUniversity Dr WAnna St01/20/25 06/30/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure59Tawakoni Dr (5908)Amistad Lnat Intersection05/19/25 06/27/25 ADA Ramp RepairStreetsRoy San MiguelLane Closure60Trinity RdMcKinney StBlagg Rd05/05/25 06/06/25 Utilities and PavementreplacementEngineeringDante HaleFull Closure61Unicorn Lake BlvdState School RdWind River Ln03/25/25 06/30/25 Sanitary sewer workPrivate DevelopmentGavin PetnerLane Closure62Union Cir (in entirety)Chestnut StPrairie St05/12/25 10/01/25 Utility installations andpavement replacement.EngineeringMegan DavidsonFull Closure63Welch StEagle DrHickory St06/03/24 06/30/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure64Welch StChestnut StMulberry St02/03/25 07/01/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure65Welch StEagle DrHighland St03/13/25 07/04/25 Utility installations andpavement replacementEngineeringMegan DavidsonFull Closure66Welch StHighland StHickory St08/26/24 07/31/25 Utility installations andpavement replacement.EngineeringScott FettigRolling Closure Exported on May 30, 2025 11:42:06 AM CDT31
Street/ IntersectionFromToClosure StartDateClosure EndDateDescriptionDepartmentDepartment Contact Closure Type67Westway StAnna StBolivar St01/24/25 06/30/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure68Willowwood StWestwood DrLeslie St03/10/25 06/18/25 Sanitary sewer, water andstorm sewer installPrivate DevelopmentGavin PetnerLane Closure Exported on May 30, 2025 11:42:06 AM CDT32
3 Street Closure Report: Completed ClosuresStreet/ IntersectionFromToClosure StartDateClosure EndDateDescriptionDepartmentDepartment Contact Closure Type1Audra LnStockton StMockingbird Ln07/29/24 05/09/25 Connection new storm drainageto existing City of Dentondrainage.Private DevelopmentZabdiel MotaLane Closure2Austin St N (208)Pecan St W@ Intersection03/31/25 05/09/25 ADA / Sidewalk Repair StreetsRoy San MiguelLane Closure3Ave CEagle DrHighland St08/26/24 04/30/25 Pavement replacement. EngineeringScott FettigFull Closure4Clear River LnMontecito DrSweet Cloud Way04/07/25 05/23/25 Concrete Panel Repair StreetsRoy San MiguelLane Closure5Eastpark BlvdLinden DrCrescent St04/28/25 05/26/25 Jobsite needs to be able toaccess the buildings withcranes but cant do that frominside jobsitePublic Works Inspections Collin ColeFull Closure6Ector StEmery StUniversity Dr04/28/25 05/26/25 Sanitary Sewer Being installedin the Northbound lanePublic Works Inspections Collin ColeLane Closure7Hillcrest StPanhandle StCrescent St12/27/23 04/30/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure8Johnson StCollins StSmith St04/14/25 05/09/25 Sewer connectionPublic Works Inspections Stephany TrammellLane Closure9Nautical LnHickory Creek RdOcean Dr04/28/25 05/27/25 Water and Storm line tie ins Private DevelopmentGavin PetnerLane Closure10Panhandle StEctor StAileen St09/27/24 05/30/25 Utility installations andpavement replacement.EngineeringScott FettigFull Closure11Ryan RdCreekside DrGranada Trl05/19/25 05/23/25 Sanitary Sewer improvement Public Works InspectionsWastewaterJohn CantuFull Closure12Saddle Back DrQuarter Horse WayHighpoint Dr04/28/25 05/15/25 Sidewalk and Panel Repairs StreetsRoy San MiguelLane Closure13Welch StOak StHickory St04/21/25 05/16/25 Mastec relocating gas lines Public Works Inspections Stephany TrammellFull Closure Exported on May 30, 2025 11:42:23 AM CDT33